background image

 

Section 3

 

Operation 

 
This section describes how to set up and use the HTT-1.

   

 

Setting up the HTT-1 

 

As shipped from the factory, the HTT-1 container contains the following items: 
 

• 

The HTT-1 Function Tester 

• 

This manual 

• 

Return cable 

• 

Optional cables, if ordered. 

 
Remove the HTT-1 from the container and place it on a non-conductive test bench.  Plug the cord 
of  the  HTT-1  into  the  receptacle  on  the  Hipot  tester  and  connect  the  return  the  front  of  the 
Compliance West hipot or continuity tester.  To begin testing, follow the directions in Section 1 
above.   

Note:    This  setup  will  work  for  any  hipot  tester  having  a  standard  wall  receptacle  and  return 
jack on the front panel. 

 
For other setups, consult the Setup Procedure below.

    

 

Front Panel Features 

 

The front panel features of the HTT-1 are shown in Figure 1 and described in Table 2. 

 

Setup Procedure:  Hipot Tester 

 

This  procedure  will  describe  connection  of  the  HTT-1  to  a  hipot  tester  or  a  combination  hipot 
tester/ground  continuity  tester.    Because  of  the  varying  types  of  tester  outputs,  cables  are  not 
provided with the HTT-1.  For custom cables, please contact Compliance West USA. 
 
1)  Connect the hipot tester to the HTT-1.   

a)  On your hipot tester, plug the HTT-1 into the high voltage receptacle. 
b)  On  your  hipot  tester,  identify  the  return  lead  of  the  high  voltage  output.    This  is 

connected to the black banana jack receptacle of the HTT-1. 

2)  Conduct a simulated PASSING test by setting all three switches of the HTT-1 to the PASS 

(green) setting and initiating a hipot test by starting your hipot tester. 
a)  Your hipot tester should indicate ‘PASS’. 

3)  If  your  tester  checks  for  ground  continuity,  conduct  a  simulated  GROUND  OPEN  test  by 

setting  the  GROUND  switch  on  the  HTT-1  to  ‘FAIL’.    (All  other  switches  on  the  HTT-1 
should be set to ‘PASS’.)  Begin testing by starting your hipot tester. 
a)  Your hipot tester should indicate ‘FAIL’, stop testing, and sound a buzzer or otherwise 

warn the operator of a problem. 

4)  Conduct  a  simulated  EXCESS  LEAKAGE  test  by  setting  the  LEAKAGE  switch  on  the 

HTT-1 to ‘FAIL’.  (All other switches on the HTT-1 should be set to ‘PASS’).  Begin testing 
by starting your hipot tester. 

Summary of Contents for HTT-1

Page 1: ...HTT 1 Function Tester Instruction Manual COMPLIANCE WEST USA...

Page 2: ...i...

Page 3: ...ons Compliance West USA is proud to present you with your HTT 1 The operating instructions are included in the Manual so please retain this information for future use Thank you for your trust and conf...

Page 4: ...ii...

Page 5: ...troduction and Specifications 2 Introduction 2 Specifications 2 Operation 3 Setting up the HTT 1 3 Front Panel Features 3 Setup Procedure Hipot Tester 3 Setup Procedure Ground Continuity Tester 4 Unan...

Page 6: ...a time to ensure that your testers are functioning correctly A proper test plan would be constituted of the following tests 1 Connect HTT 1 to the tester outputs 2 Set all three switches on the HTT 1...

Page 7: ...fication tool The HTT 1 is warranted for a period of one year upon shipment to the original purchaser Specifications Specifications for the HTT 1 are listed in Table 1 below Table 1 Specifications of...

Page 8: ...continuity tester Because of the varying types of tester outputs cables are not provided with the HTT 1 For custom cables please contact Compliance West USA 1 Connect the hipot tester to the HTT 1 a O...

Page 9: ...tester identify the return lead of the high current output This is connected to the black banana jack receptacle of the HTT 1 b On your ground continuity tester plug the HTT 1 into the high current re...

Page 10: ...5 Figure 1 HTT 1 Front Panel Features 6 5 4 3 1 2...

Page 11: ...breakdown occurred 4 Hipot Test Switch When set to FAIL a dielectric breakdown will be simulated and a spark can be seen in the Arc View window When set to PASS a normal passing result is simulated Us...

Page 12: ...ROUND LEAKAGE HIPOT Operating mode PASS PASS PASS No failure the tester connected to the HTT 1 should indicate test completion with a passing result FAIL PASS PASS Ground Fail the tester connected to...

Page 13: ...748 6224 Technical Assistance is available from Compliance West USA between the hours of 8 30 AM and 4 30 PM Pacific Time Monday through Friday Compliance West USA 2120 Jimmy Durante Blvd Suite 124 De...

Reviews: