Section 1 

An Introduction to Dielectric Withstand Testing with the HT-5000P ac/dc 

200mA 

 

 

The dielectric withstand test is a test which is recognized by safety agencies worldwide 

as  a  valid  criterion  of  safe  assembly  of  end-use  equipment.    The  HT-5000P  ac/dc  200mA  is 
designed as a research instrument to determine the dielectric properties of component assemblies 
of end-use equipment.  It applies a high-voltage potential between Output and Return test leads 
and monitors Leakage Current, and watches for Dielectric Breakdown during the test.  To aid in 
testing, the HT-5000P ac/dc 200mA can be configured with or without a test duration timer, and 
can be set to deliver high voltage after an arc has been detected to pinpoint an area of arcing. 
 
 

The  dielectric  withstand  test  involves  high  voltage,  and  caution  should  be  exercised 

when using the HT-5000P ac/dc 200mA.  The Return Receptacle on the front panel is connected 
to  ground  potential,  and  setups  should  be  designed  with  this  in  mind,  to  guard  against  the 
operator contacting high voltage.  Always make sure the return lead is firmly connected.   
 

Leakage Test 

 

 

The HT-5000P ac/dc 200mA leakage test uses a separate low-frequency circuit to detect 

excessive current between the Output and Return receptacles on the front panel.  There is not a 
specific  leakage  current  level  pass/fail  requirement  at  this  time  for  most  equipment.    However, 
higher  than  normal  leakage  current  on  a  particular  sample  may  indicate  an  assembly,  and  or  a 
component problem in the circuit.   
 
 

The  leakage  current  is  also  monitored  by  the  HT-5000P  ac/dc  200mA  to  ensure  that 

excessive  leakage  does  not  keep  the  tester  from  developing  full  voltage  required  for  the  high 
voltage test.  The HT-5000P ac/dc 200mA will provide full voltage at any leakage current level 
up to 200mA. Set the acceptable leakage current limit using the Shutdown Limit Potentiometer 
on the front panel.   
 
 

If the green Full Voltage indicator lights and the test  continue, the leakage current was 

below the acceptable limit. 

If  the  red  Excess  Leakage  indicator  lights,  the  buzzer  sounds, 

and the test is terminated; the leakage current was above the acceptable limit.   
 

High Voltage Dielectric Withstand Test 

 
 

This test checks for insulation system breakdown’s by applying a high voltage between 

the  Output  and  Return  receptacles  on  the  front  panel.    The  HT-5000P  ac/dc  200mA  uses  a 
separate high-frequency circuit to detect arc breakdowns. 
 
 

Set the test duration with the Timer Control Potentiometer on the front panel.  The test 

time is counted from the time the Full Voltage indicator is lit to the completion of the test.  The 
Timer Control Switch must be set to ON, or the HT-5000P ac/dc 200mA will test only while the 
Test  Button  is  pressed.    The  minimum  test  time  is  one  second  regardless  of  the  setting  of  the 
Timer Control Switch. 

Summary of Contents for HT-5000P

Page 1: ......

Page 2: ...i...

Page 3: ...nd ergonomic front panel and represents the latest in high voltage laboratory testing To fully appreciate all the features of your new meter we suggest that you take a few moments to review this manua...

Page 4: ...iii...

Page 5: ...ory Testing 10 Factory Settings 10 Voltage Type Selection 10 Display of Leakage Limit and Duration Settings 10 Leakage Current Level Adjust 10 Voltage Adjust 11 High Voltage Test Time Adjust 11 Settin...

Page 6: ...1...

Page 7: ...ge current level pass fail requirement at this time for most equipment However higher than normal leakage current on a particular sample may indicate an assembly and or a component problem in the circ...

Page 8: ...dicator lights a breakdown arc has been detected High Voltage Discharge The HT 5000P ac dc 200mA has an internal circuit designed to remove the high voltage after completion of the dielectric withstan...

Page 9: ...eature most be disarmed by turning the voltage knob to the minimum also the unit must be armed by pressing the red RESET button The test will not begin until the blue TEST Button is pushed If a failur...

Page 10: ...Panel Test Time Leakage Limit Voltage Adjustment Timer ON DEFEAT Hipot ON DEFEAT ENVIRONMENTAL Operating Temperature 15 40 C Relative Humidity Range 0 90 non condensing GENERAL Input power requiremen...

Page 11: ...Table 3 1 Shipment Cables Connectors Use the original shipping container for subsequent shipping If the original shipping container is not available be sure that adequate protection is provided to pre...

Page 12: ...7 Figure 3 1 Front Panel Controls Indicators and Connectors...

Page 13: ...djust knob must be at the minimum position in order to disarm the Zero Voltage Start safety feature Item 15 7 VOLTAGE METER Connected to the output Reads actual output voltage Adjust meter range with...

Page 14: ...current condition 12 Push the TEST button 13 Use the Voltage Adjust knob to increase the voltage output but the test should terminate immediately and the buzzer should sound The Excess Leakage Indica...

Page 15: ...e Selection Use the AC DC Voltage Switch This switch is functional only when the RESET or TEST button is lit Display of Leakage Limit and Duration Settings To view the Test Duration and Leakage Limit...

Page 16: ...nd Consult the safety agencies on the test time for the type of equipment being tested If a different test time is required use this procedure to set it 1 Connect the tester to a correctly rated sourc...

Page 17: ...nt under test is grounded by the HT 5000P ac dc 200mA a risk of shock exists Testing Products This section describes how to conduct a test Testing can be terminated at any time by pressing the RESET b...

Page 18: ...g as the TEST button is pressed 12 If no breakdown is detected the high voltage will be removed at the end of the test the Hipot Pass indicator will light and the RESET button will light 13 Do not dis...

Page 19: ...failures ON DEFEAT Buzzer will turn sound It will not allow to test until the Test Timer switch is in defeat DEFEAT DEFEAT Test will continue only as long as the TEST button is held in minimum one se...

Page 20: ...se is required for all in warranty repairs The manufacturer is also available for calibration and or repair of instruments that are beyond their warranty period Contact the manufacturer for a cost quo...

Page 21: ...was entered the display will read Sure if not start over at step 1 6 While Sure is displayed on the screen you can 6 1 Press Reset to exit out of the Calibration Mode and keep all of the currently pro...

Page 22: ...t 2 Select the type of output voltage with the AC DC Switch 3 Set up a 1000 1 probe with the volt meter has is shown on Figure 4 1 4 Enter to Calibration Mode See Entering Calibration Mode procedure 5...

Page 23: ...firm the new voltage meter calibration performing again the Voltage Meter Verification procedure mentioned before Leakage Meter Verification 1 Turn Off the HT 5000P ac dc 200mA unit 2 Select the type...

Page 24: ...the external current meter mA scale equals the number showed on the front meter of the HT 5000P ac dc 200mA unit then press the Test button and the front display will show hold for a few seconds wait...

Page 25: ...ce West USA is available Phone 800 748 6224 Hours 8 30 AM 4 30 PM Pacific Time Also available on our web site at www compwest com Contact Compliance West USA 650 Gateway Center Way Suite D San Diego C...

Reviews: