background image

 

Initial Checkout Procedure 

 

Use this procedure to verify that the HT-5000P ac/dc 200mA tester is working correctly.  

Refer to table 3-1, figure 3-1  and table  3-2 for location of items. 

 

CAUTION 

High voltage, risk of shock, use with care. 

 

1.

 

Turn the Tester on using the AC Power switch. 

2.

 

Set the Test Timer switch, and Failure Shutdown switch to ON position.   

3.

 

Disconnect leads from the Output and Return jacks. 

4.

 

Set the Test Time to around 30 seconds. 

5.

 

Push the RESET button. The TEST button should light. 

6.

 

Disarm the Zero Voltage Start safety feature by turning the voltage knob to the minimum. 

7.

 

Push the TEST button. 

8.

 

After the FULL VOLTAGE indicator lights, use the Voltage Adjust knob to set the desired 
output  voltage.  At  the  end  of  the  test,  the  Full  Voltage,  Hipot  Pass,  and  RESET  switch 
indicators should be lit. 

9.

 

Push the RESET button. The TEST button should light. 

10.

 

Disarm the Zero Voltage Start safety feature by turning the voltage knob to the minimum. 

11.

 

Connect  the  red  lead  to  the  Output  receptacle,  and  connect  the  black  lead  to  the  Return 
receptacle, then, connect the two leads together to simulate a high leakage current condition.  

12.

 

Push the TEST button. 

13.

 

Use  the  Voltage  Adjust  knob  to  increase  the  voltage  output,  but  the  test  should  terminate 
immediately and the buzzer should sound.  The Excess Leakage Indicator and RESET button 
indicators should be lit. 

14.

 

Disconnect  the  red  lead  (banana  connector)  from  the  HV  output  of  the  HT-5000P  ac/dc 
200mA,  but  keep  the  red  alligator  clip  connected  with  the  black  lead  which  is  already 
connected to the Return receptacle. 

15.

 

Push the RESET button. The TEST button should light. 

16.

 

Disarm the Zero Voltage Start safety feature by turning the voltage knob to the minimum. 

17.

 

Push the TEST button. 

18.

 

After  the  FULL  VOLTAGE  indicator  lights,  use the  Voltage Adjust knob to set the output 
voltage to approx. 1500 volts.  

19.

 

(This  test  simulates  a  dielectric  breakdown.  High  voltage  could  exist  on  the  alligator  clips.  
Exercise  caution  to  avoid  shock.)    Pick  up  the  red  lead  and  insert  it  into  the  HV  Output 
during the machine is performing the test. The test will immediately terminate with a buzzer.  
The Full Voltage, Hipot Fail, and RESET button indicators should be lit. 

20.

 

Push the RESET button. The TEST button should light. 

 

 
If  any  of these tests give unexpected results, service may be required. Please check the 

test setup and if further information is needed, contact our Service hotline for assistance. 

 
 
 
 
 
 
 
 

Summary of Contents for HT-5000P

Page 1: ......

Page 2: ...i...

Page 3: ...nd ergonomic front panel and represents the latest in high voltage laboratory testing To fully appreciate all the features of your new meter we suggest that you take a few moments to review this manua...

Page 4: ...iii...

Page 5: ...ory Testing 10 Factory Settings 10 Voltage Type Selection 10 Display of Leakage Limit and Duration Settings 10 Leakage Current Level Adjust 10 Voltage Adjust 11 High Voltage Test Time Adjust 11 Settin...

Page 6: ...1...

Page 7: ...ge current level pass fail requirement at this time for most equipment However higher than normal leakage current on a particular sample may indicate an assembly and or a component problem in the circ...

Page 8: ...dicator lights a breakdown arc has been detected High Voltage Discharge The HT 5000P ac dc 200mA has an internal circuit designed to remove the high voltage after completion of the dielectric withstan...

Page 9: ...eature most be disarmed by turning the voltage knob to the minimum also the unit must be armed by pressing the red RESET button The test will not begin until the blue TEST Button is pushed If a failur...

Page 10: ...Panel Test Time Leakage Limit Voltage Adjustment Timer ON DEFEAT Hipot ON DEFEAT ENVIRONMENTAL Operating Temperature 15 40 C Relative Humidity Range 0 90 non condensing GENERAL Input power requiremen...

Page 11: ...Table 3 1 Shipment Cables Connectors Use the original shipping container for subsequent shipping If the original shipping container is not available be sure that adequate protection is provided to pre...

Page 12: ...7 Figure 3 1 Front Panel Controls Indicators and Connectors...

Page 13: ...djust knob must be at the minimum position in order to disarm the Zero Voltage Start safety feature Item 15 7 VOLTAGE METER Connected to the output Reads actual output voltage Adjust meter range with...

Page 14: ...current condition 12 Push the TEST button 13 Use the Voltage Adjust knob to increase the voltage output but the test should terminate immediately and the buzzer should sound The Excess Leakage Indica...

Page 15: ...e Selection Use the AC DC Voltage Switch This switch is functional only when the RESET or TEST button is lit Display of Leakage Limit and Duration Settings To view the Test Duration and Leakage Limit...

Page 16: ...nd Consult the safety agencies on the test time for the type of equipment being tested If a different test time is required use this procedure to set it 1 Connect the tester to a correctly rated sourc...

Page 17: ...nt under test is grounded by the HT 5000P ac dc 200mA a risk of shock exists Testing Products This section describes how to conduct a test Testing can be terminated at any time by pressing the RESET b...

Page 18: ...g as the TEST button is pressed 12 If no breakdown is detected the high voltage will be removed at the end of the test the Hipot Pass indicator will light and the RESET button will light 13 Do not dis...

Page 19: ...failures ON DEFEAT Buzzer will turn sound It will not allow to test until the Test Timer switch is in defeat DEFEAT DEFEAT Test will continue only as long as the TEST button is held in minimum one se...

Page 20: ...se is required for all in warranty repairs The manufacturer is also available for calibration and or repair of instruments that are beyond their warranty period Contact the manufacturer for a cost quo...

Page 21: ...was entered the display will read Sure if not start over at step 1 6 While Sure is displayed on the screen you can 6 1 Press Reset to exit out of the Calibration Mode and keep all of the currently pro...

Page 22: ...t 2 Select the type of output voltage with the AC DC Switch 3 Set up a 1000 1 probe with the volt meter has is shown on Figure 4 1 4 Enter to Calibration Mode See Entering Calibration Mode procedure 5...

Page 23: ...firm the new voltage meter calibration performing again the Voltage Meter Verification procedure mentioned before Leakage Meter Verification 1 Turn Off the HT 5000P ac dc 200mA unit 2 Select the type...

Page 24: ...the external current meter mA scale equals the number showed on the front meter of the HT 5000P ac dc 200mA unit then press the Test button and the front display will show hold for a few seconds wait...

Page 25: ...ce West USA is available Phone 800 748 6224 Hours 8 30 AM 4 30 PM Pacific Time Also available on our web site at www compwest com Contact Compliance West USA 650 Gateway Center Way Suite D San Diego C...

Reviews: