background image

 

 

18 

Operation/Lamp Function Test 

 

Use the following procedure to determine proper operation of the UUT and Lamps of the GF-30AC-T: 
 
1.  Connect the UUT to a proper source of supply using the included 18 AWG power supply cord. 
2.  Disconnect all other leads and turn the UUT on. 
3.  Verify the blue lamp is lit. 
4.  Push the Test button and hold. 
5.  Verify the red lamp is lit and the internal buzzer sounds. 
6.  Using  a  test  lead,  short  the  ground  of  the  front  panel  test  power  receptacle  to  the  return  lead 

receptacle. 

7.  Press the Test button briefly. 
8.  Verify the green lamp is lit and the buzzer is not sounding.

 

 

Current Output Test 

 

1. 

Plug the Test Power Cord and the Test Return Lead into the front panel. 

2. 

Connect the Test Return Lead and the ground of the IEC Test Cordset to the back panel calibration 
resistor using the alligator clip/wire assembly. 

3. 

Connect the DMM across the calibration resistor. 

4. 

Push and hold the Test Button on the front panel.  For a 25 amp output, the DMM should read 2.5 
volts ac   3%.

 

 

NOTE 

If these tests confirm proper operation, the tester must be adjusted as shown in Section 2 above before 

use.

 

 

Calibration Procedure 

 

The Calibration Procedure should be used any time your instrument has been repaired or fails to pass the 
performance test.  During the calibration procedure, the tester is referred to as the UUT. 

 

NOTE 

Allow the instrument to stabilize for approximately five minutes.  Perform all calibration adjustments at 

an ambient temperature of 23 C  5 C (73 F  9 F).

 

 

WARNING 

CALIBRATION ADJUSTMENTS ARE PERFORMED ON ENERGIZED CIRCUITS.  

EXERCISE CAUTION AT ALL TIMES, AND USE A NON-CONDUCTIVE TOOL FOR ALL 

ADJUSTMENTS.

 

 

At the start of the calibration procedure, remove the two upper screws on each side of the GF-30AC-T, 
and remove the top cover. 

 

Summary of Contents for GF-30AC-T

Page 1: ...GF 30AC T Ground Circuit Tester Instruction Manual...

Page 2: ...represents the latest in high current production line testing To fully appreciate all the features of your new meter we suggest that you take a few moments to review this manual Compliance West USA s...

Page 3: ...3...

Page 4: ...Duration Adjustment 12 Operating Techniques 12 Setting the Test Time Duration 12 Testing the EUT 12 Test results 13 Green Light 13 Red Light 13 Red Light and Buzzer Sound 13 Simultaneous Red and Gree...

Page 5: ...etermined amount of time after the Test Button has been released The instrument advises the operator of any internal malfunction affecting the output A one time setup procedure allows the instrument t...

Page 6: ...est Duration Timer 0 25 sec approx Duty cycle 100 ENVIRONMENTAL Operating Temperature 15 35 C Relative Humidity Range 0 90 non condensing GENERAL Input power requirements See rear panel for input volt...

Page 7: ...rotection is provided to prevent damage during shipment We recommend that the instrument be surrounded by at least one inch of shock absorbing material on all sides of the container Remove the Tester...

Page 8: ...Red Fail Indicator Lamp Incandescent lamp When lit indicates that equipment under test has more than 100 milliohms in grounding path or is incorrectly connected to tester Replace with 6 3V type 86 la...

Page 9: ...section of this manual for procedure 5 Appliance Inlet Fuseholder Power Switch Use 18 AWG cordset to connect tester to appropriate source of supply Replace line fuse Turn tester ON OFF 6 Fuse replacem...

Page 10: ...ductive surface Push the Test button The GF 30AC T should indicate a Fail by lighting the red light and sounding the internal buzzer If your Tester yielded the proper results it is working properly If...

Page 11: ...safety agency inspection personnel Adjusting the Pass Fail Point for products with non removable power cords Use this adjustment procedure if the equipment under test uses a non detachable power cord...

Page 12: ...t will continue for the amount of time set during this Procedure after the Test Button is released Therefore we recommend that the Test Duration control be adjusted to its minimum position when a manu...

Page 13: ...the ground system of the EUT has less than 100 milliohm resistance For most categories of equipment this result is acceptable Red Light A red light indicates the ground system of the EUT has more than...

Page 14: ...er operation by following steps 1 3 in Adjusting the Pass Fail Point using the supplied Test Cordset Press the Test Button and measure the voltage across the calibration resistor If the unit is workin...

Page 15: ...st USA is available Phone 800 748 6224 Hours 8 00 AM 4 00 PM Pacific Time Also available on our web site at www compwest com Contact Compliance West USA 650 Gateway Center Way Suite D San Diego CA 921...

Page 16: ...The Test equipment required for both the performance test and calibration is a DMM able to read true rms 0 3 VAC 1 Service Information The GF 30AC T is warranted to the original purchaser for a perio...

Page 17: ...iagram for high voltage areas Cleaning CAUTION Do not use aromatic hydrocarbons or chlorinated solvents for cleaning These solutions will react with the plastic materials used in the instrument Clean...

Page 18: ...el calibration resistor using the alligator clip wire assembly 3 Connect the DMM across the calibration resistor 4 Push and hold the Test Button on the front panel For a 25 amp output the DMM should r...

Page 19: ...libration resistor is 2 5 Vrms Using Ohms law this corresponds to an output current of 25 Amps Other output current levels can be set in the same manner Adjust Buzzer 5 With the calibration resistor s...

Reviews: