Calibration Access 

 

Use the following procedures to gain access to the calibration adjustments of your instrument. 
 
1.  Set Line Power switch to OFF. 
2.  Disconnect the power cord from the rear of the instrument. 
3.  Remove the two upper screws on each side of the unit. 
4.  Grasp the top of the enclosure clamshell and lift it off the front and rear panels.  
5.  Slide the rear panel / PWB assembly upward until it is clear of the bottom enclosure clamshell. 
6.  All calibration adjustments are now accessible. 
7.  To reassemble, reverse steps 1-6 above.

 

 

NOTE 

With the power cord replaced, the instrument is operational for service.

 

 

WARNING 

Dangerous voltages exist inside the enclosure when energized.  Exercise extreme care when 

working on an energized circuit.  See PWB layout diagram for high voltage areas. 

 

 

Cleaning 

 

CAUTION 

Do not use aromatic hydrocarbons or chlorinated solvents for cleaning.  These solutions will react with 

the plastic materials used in the instrument.

 

 
Clean the front panel and case with a mild solution of detergent and a damp sponge.  Clean dust from the 
PWB with clean, dry, low pressure (<20 psi).Performance Test 
 
The performance test compares the performance of your instrument with the list of specifications given 
in  Section  1.    This  test  is  recommended  for  incoming  inspection, as a preventative maintenance check, 
and to verify the specifications.  It is not necessary to disassemble the instrument to conduct these tests.  
If the instrument fails any part of the performance test, calibration and / or repair is indicated. 
 
Allow the instrument to stabilize and perform the test at an ambient temperature of 23 C  5 C (73 F  9
F).  During the performance test (and the calibration procedure) your Tester is referred as the UUT. 

 

Summary of Contents for GF-30AC-T

Page 1: ...GF 30AC T Ground Circuit Tester Instruction Manual...

Page 2: ...represents the latest in high current production line testing To fully appreciate all the features of your new meter we suggest that you take a few moments to review this manual Compliance West USA s...

Page 3: ...3...

Page 4: ...Duration Adjustment 12 Operating Techniques 12 Setting the Test Time Duration 12 Testing the EUT 12 Test results 13 Green Light 13 Red Light 13 Red Light and Buzzer Sound 13 Simultaneous Red and Gree...

Page 5: ...etermined amount of time after the Test Button has been released The instrument advises the operator of any internal malfunction affecting the output A one time setup procedure allows the instrument t...

Page 6: ...est Duration Timer 0 25 sec approx Duty cycle 100 ENVIRONMENTAL Operating Temperature 15 35 C Relative Humidity Range 0 90 non condensing GENERAL Input power requirements See rear panel for input volt...

Page 7: ...rotection is provided to prevent damage during shipment We recommend that the instrument be surrounded by at least one inch of shock absorbing material on all sides of the container Remove the Tester...

Page 8: ...Red Fail Indicator Lamp Incandescent lamp When lit indicates that equipment under test has more than 100 milliohms in grounding path or is incorrectly connected to tester Replace with 6 3V type 86 la...

Page 9: ...section of this manual for procedure 5 Appliance Inlet Fuseholder Power Switch Use 18 AWG cordset to connect tester to appropriate source of supply Replace line fuse Turn tester ON OFF 6 Fuse replacem...

Page 10: ...ductive surface Push the Test button The GF 30AC T should indicate a Fail by lighting the red light and sounding the internal buzzer If your Tester yielded the proper results it is working properly If...

Page 11: ...safety agency inspection personnel Adjusting the Pass Fail Point for products with non removable power cords Use this adjustment procedure if the equipment under test uses a non detachable power cord...

Page 12: ...t will continue for the amount of time set during this Procedure after the Test Button is released Therefore we recommend that the Test Duration control be adjusted to its minimum position when a manu...

Page 13: ...the ground system of the EUT has less than 100 milliohm resistance For most categories of equipment this result is acceptable Red Light A red light indicates the ground system of the EUT has more than...

Page 14: ...er operation by following steps 1 3 in Adjusting the Pass Fail Point using the supplied Test Cordset Press the Test Button and measure the voltage across the calibration resistor If the unit is workin...

Page 15: ...st USA is available Phone 800 748 6224 Hours 8 00 AM 4 00 PM Pacific Time Also available on our web site at www compwest com Contact Compliance West USA 650 Gateway Center Way Suite D San Diego CA 921...

Page 16: ...The Test equipment required for both the performance test and calibration is a DMM able to read true rms 0 3 VAC 1 Service Information The GF 30AC T is warranted to the original purchaser for a perio...

Page 17: ...iagram for high voltage areas Cleaning CAUTION Do not use aromatic hydrocarbons or chlorinated solvents for cleaning These solutions will react with the plastic materials used in the instrument Clean...

Page 18: ...el calibration resistor using the alligator clip wire assembly 3 Connect the DMM across the calibration resistor 4 Push and hold the Test Button on the front panel For a 25 amp output the DMM should r...

Page 19: ...libration resistor is 2 5 Vrms Using Ohms law this corresponds to an output current of 25 Amps Other output current levels can be set in the same manner Adjust Buzzer 5 With the calibration resistor s...