3-22
Rack-Mount Server Installation
For use with Intel Pentium II Xeon processor-based servers only
Writer: Salvo Project: Compaq ProLiant 5500 Servers Setup and Installation Guide Comments: 328470-001\July 1998
File Name: D-CH03.DOC Last Saved On: 7/6/98 4:04 PM
COMPAQ CONFIDENTIAL - NEED TO KNOW REQUIRED
Loading the Rack Server
Load and secure the server to the rack with the face plate thumbscrews before
continuing to attach any more mounting bracket assemblies. Ensure that this
pair of brackets is perfectly aligned and installed and that the server fits before
you continue.
WARNING:
To reduce the risk of personal injury or damage to
the equipment, a minimum of two people
MUST
lift the server
into the rack. The server weighs in excess of 92 lb (41.8 kg). If
the unit is to be loaded above chest level, a third person must
assist in aligning the rails while the other two support the unit.
IMPORTANT:
To make the server lighter and more manageable, do not
install drives in the server until after you load the server into the rack. You
may also temporarily remove power supplies and reinstall them after you
have mounted the server in the rack.