CLiC-iT 89 User Instruction Download Page 11

11

must either be fixed to the harness attachment point or be connected to the lanyards, 

avoiding that the two lanyards be tensioned in the event of a fall.

In this case, the difference between the two anchor point must be 20 cm minimum.

Life safety systems should limit a user's fall to less than 50 cm (20 inches). 

According to the lifeline height & to the size of the participant, we propose following 

recommendations: 

Install the central point of the lanyard below the neck 

                 OR

Install the central point of the lanyard above the neck

Details : see point 4.1 

Handles are recommended on all the game to eliminate the need for users to grab the 

lanyards. Lifelines should be installed to minimize obstruction of a user’s head, for 

example on the side.

Choosing PPE

It is recommended that the central point of CLiC-iT lanyard be attached with the shortest 

possible distance to the user’s harness clip-in point. A low clip-in point of the lanyard on 

the harness is strongly recommended to decrease the risk of neck entrapment.

It must be considered that helmets may make it more difficult to extricate one’s head 

from between the lanyard legs. 

Fitting of PPE to the participant 

The correct harness and lanyard length must be chosen individually to fit each partici-

pant correctly.

Harness must be put on properly and double checked.

Adjustments to the harness leg loops are necessary to prevent the harness clip-in point 

from sliding upwards in the case of a fall. This harness rise should be taken into consi-

deration and planned for.

The user should be instructed on proper harness fit and to ask a guide if something feels 

wrong. It should be forbidden for participants to put on the harness on their own. 

Training of the staff 

All staff members must be aware of their responsibilities in order to establish a safe 

environment. They must be properly trained in assist and rescue techniques as well as in 

briefing and coaching methods. 

All staff must receive professional training regularly in which all information for the 

proper operation of the park is conveyed. 

Assessments of the staffs ability to perform competent rescue procedures and conduct 

proper and complete guest briefings must be done on a regular basis. 

The Awareness of all involved risks throughout the park must be raised within your 

instructor and rescue team. The staff must know all possible dangers associated with 

using life safety systems and how different components interact with each other. 

A helpful and supportive attitude towards the guests is important.

Briefing 

The instructions must be passed on to each user on how to use all the equipment and 

practice handling it on the ground before climbing. Awareness of all risks must be 

raised. The user must be informed to refrain from placing his/her head between the 

lanyard legs.

The user should be encouraged to push the lanyard forward him/her on the cable so 

that the lanyard stays in the front of the body and the user's head remains away from 

lanyards. 

Carabiners should only be attached to the designated lifelines. 

Supervision 

The staff team must be vigilant, have taken part in the training process and is required to 

have experience in supervising the course.

Good supervision covering all parts of the course must be ensured.

The rescue team must be prepared and capable of reacting quickly in case of emergency 

and have good and fast access to all parts of the course. All instructors should carry a 

system or device for lifting, not just rescuers or rescue teams.

Participants who faced difficulties during the briefing must be given additional attention 

and helped, verbally or physically, if needed.

Participants should not be left alone on a course.

Enhanced supervision must be in place where the participants are faced with special 

circumstances (zipline, Tarzan swing, etc). 

Please note

The list of recommendations stated here above is only to be used as a general guideline 

to limit the risks involved with climbing in adventure parks. This guideline is by no 

means exhaustive. It should be taken into consideration and validated by park builders 

and operators and shall continuously be expanded in accordance with feedback and 

experiences. 

It is the responsibility of all involved parties to minimize the inherent risks involved with 

climbing and using personal protective equipment, including but not limited to following 

all instructions and guidelines, ensuring a safe park design, a thorough briefing for users, 

the compatibility between all products, the correct use of the safety equipment and by 

providing appropriate training and sufficient qualified staff and life safety personnel to 

oversee the operation (this list is not exhaustive with the practice of the ropes course). 

Summary of Contents for 89

Page 1: ...ouvrable C8 Swivel C8 openable swivel C8 4 5 6 7 8 9 Références Anneau de montagne C O DAS060 Elingue C 1 DAS060 EL Emerillon C 8 DAS070 Emerillon C 8 DAS132 Maillon rapide inox conforme à EN 12275 MRNI07 0 References Climbing sling C O DAS060 Sewn sling C 1 DAS060 EL Swivel C 8 DAS070 Openated swivel C 8 DAS132 Quicklink stainless steel in accordance with EN 12275 MRNI07 0 Ref L1 cm L2 cm A cm B ...

Page 2: ...ion Use 3 1 Fixer un connecteur Attach a connector 3 3 S engager sur une ligne de vie Starting on a route 3 4 Sortir de la ligne de vie Leaving a route 3 2 Ouvrir un connecteur Open a connector Connecteur 21 Connector 21 Connecteur 25 Connector 25 1 2 1 2 1 2 1 2 3 5 Faire un noeud en tête d alouette Fastening the loop with a lark s foot knot or girth hitch 3 1 2 3 4 1 3 5 2 4 2 1 1 2 3 2 VERSO 6 ...

Page 3: ...3 3 7 Manoeuvres interdites Forbidden maneuvers 2 1 3 1 2 3 4 5 6 7 8 9 10 11 12 13 3 6 Briefing Briefing ...

Page 4: ...me CLiC iT Unlocking the CLiC iT system 4 3 Evacuation en cas d urgence Evacuation 4 5 Contrôle du produit Checking the product 1 2 3 4 5 6 7 8 9 10 11 C ZAM L C CONNECT V2 C STOP C OFF Connecteur 21 Connector 21 Connecteur 25 Connector 25 1 Aimant Magnet B X cf 1 1 L2 B X cf 1 1 Xmin L2 35cm ET AND Xmax L1 10cm Pacemaker A B Variante 1 Variante 2 2 3 X X B L 2 B X ...

Page 5: ...aires Complementary information 4 6 Nettoyage et lubrification des connecteurs Cleaning and lubrification of connectors Fabricant Manufacturer DEHONDT SARL Adresse 7 rue Pierre Pflimlin 51100 REIMS Téléphone 03 26 47 11 34 E mail contact clic it eu N individuel d identification Individual identification number Examen périodique et historique des réparations Periodic review and repairs history Temp...

Page 6: ...r 1 Fermez le connecteur ouvert sur la ligne de vie 2 Ouvrez le second connecteur en appuyant sur sa gâchette 3 Fermez le connecteur sur la ligne de vie Veillez a ce que l utilisateur connecte bien ses deux connecteurs a la ligne de vie au début du parcours 3 4 Sortir de la ligne de vie Procédure a réaliser uniquement en dehors de la zone de danger de chute Respecter les consignes de sécurité appl...

Page 7: ...le 4 Nettoyage des longes Frotter avec une brosse souple non agressive Ne pas utiliser d eau 5 Séchage Tout équipement humide doit être séché dans un endroit sec et aéré a distance de toute source de chaleur directe Un équipement humide ou qui a subi l action du gel a des caractéristiques techniques réduites 6 Stockage et transport Stocker et transporter dans un endroit frais et sec a l ombre Evit...

Page 8: ...recevoir une formation professionnelle régulièrement dans la quelle toutes les informations pour le bon fonctionnement du parc sont transmises Des évaluations de compétence du personnel pour effectuer les procédures de sauve tage et les séances d information clients doivent être effectuées sur une base régulière La prise de conscience de tous les risques associés a l ensemble du parc doit être sou...

Page 9: ...connects well both connectors on the lifeline at the beginning of the course 3 4 Leaving a route Procedure for releasing the connectors from the cable to be performed only in a safe area Follow the safety instructions applicable to the area in question 1 Unclick a connector by pressing its trigger 2 Click it on the free cable end or on the way out C OFF reference DAS044 Pull it out of the cable en...

Page 10: ...from SARL It is forbidden to modify or repair this product yourself without prior training and written authorisation from SARL DEHONDT one week after the training Life expectancy The life expectancy corresponds to the storage time before use time in use Storage time in proper storage conditions this product may be stored for 5 years before first use without affecting its lifetime in use Storage an...

Page 11: ...out the park must be raised within your instructor and rescue team The staff must know all possible dangers associated with using life safety systems and how different components interact with each other A helpful and supportive attitude towards the guests is important Briefing The instructions must be passed on to each user on how to use all the equipment and practice handling it on the ground be...

Page 12: ...u öffnen 1 Haken Sie den offenen Karabiner am Stahlseil ein und schließen ihn 2 Öffnen Sie den zweiten Karabiner durch Drücken auf den Auslöser 3 Haken ihn auf dem Seil neben dem ersten Karabiner ein Stellen Sie sicher dass der Nutzer am Beginn eines Parcours beide Karabiner richtig am Sicherungsseil einhakt 3 4 Ausstieg am Ende eines Parcours Diese Prozedur darf nur außerhalb jeglicher Absturzgef...

Page 13: ...n der Karabiner überprüft werden Es ist besonders wichtig zu überprüfen dass 1 Die beiden Karabiner auf keinen Fall gleichzeitig entriegelt werden können 2 Die Karabiner nur auf Verankerungspunkten aus Stahl magnetisierbar eingehakt werden können für die Variante Ax1 Für Ax2 Varianten Der Karabiner lässt sich nur am C ZAM Ring einhaken 3 Es ohne Drücken des manuellen Auslösers nicht möglich ist ei...

Page 14: ...bindungsbänder oberhalb des Halses ODER Installieren des zentralen Punkts der Verbindungsbänder unterhalb des Halses Details Siehe Punkt 4 1 Festhaltemöglichkeiten sind für alle Elemente empfohlen damit sich die Benutzer sich nicht an den Verbindungsbändern festhalten müssen Die Seilsicherungen müssen so installiert werden dass der Kopf des Benutzers nicht zwischen beide Verbindungsbänder gerät be...

Page 15: ...para la apertura de 1 conector 1 Enganche el conector abierto en la línea de vida 2 Abrir el segundo conector accionando el gatillo 3 Cierre el conector sobre la línea de vida Cerciorarse de que el usuario conecte bien los dos conectores sobre la línea de vida al principio del recorrido 3 4 Desconectarse de la línea de vida para salir de un recorrido Estos pasos so lo pueden realizarse en zonas si...

Page 16: ...ones de uso Evitar cualquier roce con partes abrasivas o cortantes ya que podría dañar el producto Evitar el contacto con productos químicos especialmente los ácidos que pueden des truir las fibras de los cabos sin que sea visible 4 Limpieza de los cabos Frotar con un cepillo suave no agresivo No utilizar agua 5 El secado Cualquier equipo hu medo debera ponerse a secar en un lugar seco y ventilado...

Page 17: ...o de un ambiente seguro Deben estar correctamente formados en las te cnicas de asistencia y rescate asi como en los me todos de informacio n y de brieffing Todo el personal debe recibir regularmente una formacio n profesional en la cual se transmiten todas las informaciones necesarias para el buen funcionamiento del parque Deben realizarse regularmente evaluaciones de competencias del personal par...