Room thermostat

Preparation

The whole system should be thoroughly flushed to remove any
debris that may be in the supply pipework to the HIU and to
the domestic hot water and heating pipework in the apartment
before connecting the HIU.

Fix the HIU to the wall

N.B.

: the wall anchors (not supplied) can only guarantee

effective support if inserted correctly (in accordance with good
technical practice) into walls built using solid or semi-solid
bricks. If working with walls built using perforated bricks or
blocks, mobile dividing panels or any masonry walls other than
those indicated, a preliminary static test must be carried out on
the support system. 

Isolation Valves

Depending on the specification ordered, the HIU may be
supplied with a variety of isolation valves. We recommend that
all connections are fitted with isolation valves to allow any
maintenance work to be carried out. 

We would also recommend that the primary system includes a
flushing bypass, with an isolation valve, immediately upstream
of the HIU, to allow the primary system to be flushed prior to
the first operation of the unit.

Electrical Connections

Make sure that the electrical system can withstand the
maximum power consumption of the appliance, with particular
emphasis on the cross-section of the cables.

If in doubt, contact a qualified technician to thoroughly check
the electrical system.

Electrical safety of the appliance is only achieved when it is
correctly connected to an effective earthing system,
constructed as specified in current safety regulations. This is a
compulsory safety requirement.

Connection to the main supply

The device is supplied with an electric supply cable - plug not
supplied.

The device should be electrically connected to a 230 V (ac)
single phase + earth mains supply using the three-wire cable
marked with the label as specified below, observing the LIVE (L)
- NEUTRAL (N) polarities and the earth connection. 

This line must be connected to a circuit breaker device.   

Connection to the timeclock/thermostat

The SATK series HIU includes a connection, suitable for a time
clock/thermostat, allowing the tenant to control individual
apartment heating requirements

The connection to this device (potential-free contact) must be
made with the two-wire cable marked with the label as
specified below.

Should it be necessary to extend this cable, use one with the
same cross-section (max 1 mm²) and maximum length 30 m.

First Operation

Filling the central heating system

Open the isolation valves on the connections to the
centralised boiler plant to fill and pressurise the system to the
design pressure.

Once completed, vent the system and check the system
pressure again, repeat the filling process if necessary.

Filling the secondary circuit (SATK30103 & SATK30105 only)

The SATK30103 and SATK30105 HIUs are fitted with a filling
loop complete with double check valve and isolation valves.

The first time the system is filled, or for re-pressurising
following a heating circuit pressure switch fault indication,
restore the system pressure (1.2 to 2 bar) by opening the cock
(A) and monitoring the value using the pressure gauge (B).

Once the correct pressure has been reached, close the cock
(A), vent the system and check its pressure again, repeat the
filling process if necessary.

NOTE:

For UK markets, a filling loop is supplied in lieu of the

back-flow preventer.

Electrical supply:
230 V(ac) ±10% - 50 Hz

A

B

Summary of Contents for Altecnic SATK20

Page 1: ...SATK20 SATK30 heat interface unit Installation Operation Maintenance Instructions...

Page 2: ...roduct range 1 Safety instructions 1 Dimensions and technical speci cation 3 Installation 4 First operation 5 Electronic controller 6 Safety and alarms 7 SATK20103 and SATK20203 components 8 SATK20303...

Page 3: ...e operation of the device and or system NOTE Risk of electric shock Live parts Shut off the electric supply before opening the HIU cover 1 During installation and maintenance operations always avoid d...

Page 4: ...Dimensions SATK30 A B C kg G B G B G B 16 A B C kg G B G B G B 19 550 A A B B 65 65 450 C C 59 101 160 65 190 195 430 15 490 46 10 245 110 265 110 85 A A B B 629 65 65 550 C C 159 101 160 65 290 195 5...

Page 5: ...changer brazed stainless steel Installation The SATK series HIUs are designed for installation in a sheltered domestic environment or similar therefore cannot be installed or used outdoors i e in area...

Page 6: ...ent Connection to the main supply The device is supplied with an electric supply cable plug not supplied The device should be electrically connected to a 230 V ac single phase earth mains supply using...

Page 7: ...e cover close the isolating valves empty the HIU using the drain cocks provided remove the spacer piece A remove the blanking plug B install the ow probe in the 1 4 pocket B provided install the ow me...

Page 8: ...vated the circulation pump shuts down and the and the regulating valve closes Heating cycle activation is indicated by a ashing fault LED on the electronic controller This fault does not affect the ge...

Page 9: ...d Safety valve fault Error code 76 SATK20103 LOW temperature Removing a fault Normal operating conditions are restored automatically once the faulty safety valve is working correctly again Safety sett...

Page 10: ...tic water preheating function Heating cycle modulating temperature regulation with compensated set point floor slab heating function Factory settings Components SATK20203 MEDIUM Temperature HIU Item C...

Page 11: ...ds the drying of the under oor heating screed at low temperatures This function can only be activated and executed if there are no faults It can be activated by pressing and holding the RESET button f...

Page 12: ...al load under control The thermal response time of the system is thus minimised Safety and alarms Error codes associated with faults signalled by the lighting up of the FAULT LED are also shown on the...

Page 13: ...The function is enabled by setting dip switch 5 to the ON position During periods when the domestic water cycle is not used if the DHW probe detects a temperature 10 C below the SET value the control...

Page 14: ...eturn temperature sensor 22 Pressure gauge 23 Filling loop isolation valve 24 Filling loop double check valve 25 Filling loop Not shown on Components illustration Functional characteristics SATK30103...

Page 15: ...rying of the under oor heating screed at low temperatures This function can only be activated and executed if there are no faults It can be activated by pressing and holding the RESET button for 8 sec...

Page 16: ...l maintenance procedures should be carried out by an authorised technician Regular maintenance guarantees better ef ciency and helps to save energy Before carrying out any maintenance repair or part r...

Page 17: ...the new probe Reconnect the connector respecting the only possible way it can be inserted When carrying out maintenance on the electrical system for the connections follow the diagram on page 16 Afte...

Page 18: ...HW production valve actuator x x x x Thermal safety relief valve x x Thermal safety thermostat x x Heating flow temperature probe x x x x x x x x x x x x x x x Electric supply 230 V ac x x x x x x x x...

Page 19: ...artly clogged call quali ed personnel to have it serviced modulating valve actuator faulty call quali ed personnel to have it replaced valve obturator blocked in intermediate position call quali ed pe...

Page 20: ...valves terminals closed open the valves centralised system temperature insuf cient contact person in charge of system electronic controller not working call quali ed personnel to have it replaced prim...