Connecting mains power
z
Route the capillary tubes through the cable duct and
unroll to the required length.
z
Feed capillary tubes to the boiler test ports.
V
Feed each sensor into the corresponding sensor well
and secure it with its sensor holder (detailed view in
Æ
Fig. 53 has been turned through 180°).
V
Screw cable duct (see detailed view
Æ
Fig. 54) on the
left and right of the boiler rear panel.
Fig 53 Fastening the electrical leads
1
Sensor wells
2
Sensor holder
3
Cable duct
4
Cable clip
z
Make an electrical connection in accordance with the
wiring diagram. Take care to ensure correct cable and
capillary tube routing.
z
Insert cable clips with cable inside into the clip frame
and secure by clamping it with the tab.
Fitting the rear panel section and terminal cover
z
If necessary, push/cut the knock-out section out of the
rear panel section.
z
Hook the lower hook on the rear panel section into the
clip frame and apply pressure at the top until the side
hooks click into place.
z
Screw terminal cover onto the control panel base
again.
Fig 54 Fitting the rear panel section
1
Side hook
2
Rear panel section (control panel)
Caution: Equipment damage
through damaged capillary tubes.
z
Ensure that the capillary tubes are not
bent or crushed when unrolling and laying
them.
Make a secure electrical connection to
EN 50165 or the relevant international
installation standards and local regulations.
Secure all cables with cable clips.