Installation and maintenance instructions Logano GE315 • Issue 02/2006
We reserve the right to make any changes due to technical modifications.
Fig. 19
Return header installation
Fig. 20
Sensor well installation
1
3
4
5
2
11
2
2.4.4
Slide the return header into place (carton of
installation components)
z
Pull flat seal (Fig. 19,
) over the return header
).
z
Insert the return header from the front into the upper
boiler hub.
z
Close the pipe with a blanking flange (Fig. 19,
).
2.4.5
Sealing the sensor well
Sensor well ¾"
z
Seal the sensor well ¾" (Length: 110 mm) (Fig. 20,
) from above into the ¾" threaded hole of the
flow connection (Fig. 20,
Item 2
).
NOTE!
The profile (Fig. 19,
Item 3
) on the end
plate of the feed pipe must engage into the
recess of the upper boiler hub (Fig. 19,
Item 5
). This secures the feed pipe so, that
the feed pipe exit port is positioned at
a right angle to the boiler. This ensures
optimum water distribution in the area of
the upper boiler hub.