5 | Installation
Büchi Labortechnik AG
40/78
Operation Manual Rotavapor® R-250 Pro
Precondition:
R
Make sure that the sensors you wish to active
are connected to the instrument.
u
Push and hold the up button.
u
Set the On /off master switch to On.
ð
The instrument shows the status for the
cooling water flow sensor.
+
u
Tap the up button to change the status for the
cooling water sensor according the
requirements.
u
Tap the Aerate button on the interface.
ð
The setting for the cooling water sensor is
saved.
ð
The instrument shows the status for the level
sensor 1.
AERATE
u
Tap the up button to change the status for the
level sensor 1 according the requirements.
u
Tap the Aerate button on the interface.
ð
The setting for the level sensor 1 is saved.
ð
The instrument shows the status for the level
sensor 2.
AERATE
u
Tap the up button to change the status for the
level sensor 2 according the requirements.
u
Tap the Aerate button on the interface.
ð
The setting for the level sensor 2 is saved.
ð
The setting menu close.
AERATE
5.9
Preparing the instrument for remote control (option)
Precondition:
R
The cover is available. See Chapter 12.2 "Spare
parts and accessories", page 61
R
An extension cable is available. See
Chapter 12.2 "Spare parts and accessories",
page 61
u
Remove the interface from the instrument.
u
Disconnect all communication cables.