Minimum One Inlet and One Outlet Air Supply is Required
May be in any Combination Shown

Inlet Air Opening Must be Within12 in. (304.8mm) of  floor

Outlet Air Opening Must be Within12 in. (304.8mm) of ceiling

(1) 1 Square Inch per 4000 BTUH

(2) 1 Square Inch per 2000 BTUH

This installation NOT approved in Canada

Gas Vent

Gable Vent

Ventilated Attic

Top Above Insulation

alternate Inlet Air (1)

Ventilated Crawl Space

Outlet Air (1)

Soffit Vent

Outlet
Air (1)

Inlet
Air (1)

Outlet
Air (2)

Inlet
Air (2)

Gas Vent

Inlet
Air (2)

Soffit Vent

Gas Vent

Gable Vent

Ventilated Attic

Top Above Insulation

Inlet
Air (1)

OutletAir (1)

alternate Inlet Air (1)

A07704

Fig. 5 -- Outside Air

(This is ONLY a guide. Subject to codes of country having jurisdiction).

COMBUSTION & VENTILATION AIR

For Single Pipe Installation

CARBON MONOXIDE POISONING HAZARD

Failure to follow this warning could result in personal injury or

death.
Use methods described here to provide combustion and

ventilation air.

!

WARNING

Furnaces require ventilation openings to provide sufficient air for

proper combustion and ventilation of flue gases. All duct or

openings for supplying combustion and ventilation air must

comply with the gas codes, or in the absence of local codes, the

applicable national codes.
Combustion and ventilation air must be supplied in accordance

with one of the following:

NOTE

:

The Combustion & Ventilation Air Section in this

document, uses tables and information from the ANSI
Z223.1/NFPA 54. For use in Canada, use CSA B149.1 for this
information.

1. Section 9.3, Air for Combustion and Ventilation, of the

National

Fuel

Gas

Code,

(NFGC),

ANSI

Z223.1--2009/NFPA 54--2009 in the U.S.,

2. Sections 8.2, 8.3, 8.5, 8.6, 8.7, and 8.8 of National Stand-

ard of Canada, Natural Gas and Propane Installation Code

(NSCNGPIC), CSA B149.1--10 in Canada,

3. Applicable provisions of the local building code.

This furnace can NOT be common vented or connected to any

type B, BW or L vent or vent connector, nor to any portion of a

factory--built or masonry chimney. Multistory venting is NOT

permitted.

If

this

furnace

is

replacing

a

previously

common-vented furnace, it may be necessary to resize the

existing vent and chimney to prevent oversizing problems for the

other remaining appliance(s). See

“Venting and Combustion Air

Check”

in this section

.

This furnace MUST be vented to the

outside.
When the installation is complete, check that all appliances have

adequate combustion air and are venting properly. See

Venting

And Combustion Air Check

in “

Gas Vent Installation”

Section in

this manual.

Outdoor Combustion Air Method

A space having less than 50 cubic feet per 1,000 BTUH (4.8

M

3

/kW) input rating for all gas appliances installed in the space

requires outdoor air for combustion and ventilation.

Air Openings and Connecting Ducts

1. Total input rating for all gas appliances in the space

MUST

be considered when determining free area of open-

ings.

2. Connect ducts or openings directly to the outdoors.
3. When screens are used to cover openings, the openings

MUST

be no smaller than

1

/

4

(6 mm) mesh.

4. The minimum dimension of air ducts

MUST NOT

be less

than 3

(76 mm).

5. When sizing a grille, louver, or screen use the free area of

opening. If free area is

NOT

stamped or marked on grill or

louver, assume a 20% free area for wood and 60% for met-

al. Screens shall have a mesh size not smaller than

1

/

4

(6

mm) .

Confined Space Installation

NOTE

: A confined space is defined as an area with less than 50

cubic feet per (1.4

3

M) 1,000 BTUH (2.33 cm

2

/kW) input rating

for all gas appliances installed in the area.

Requirements

1. Provide the space with sufficient air for proper combustion

and ventilation of flue gases using horizontal or vertical

ducts or openings.

2.

Fig. 5

illustrates how to provide combustion and ventila-

tion air when two permanent openings, one inlet and one

outlet, are used.

a. One opening

MUST

commence within 12

(305 mm)

of the floor and the second opening

MUST

commence

within 12

(305 mm) of the ceiling.

b. Size openings and ducts per

Table 1

.

c. Horizontal duct openings require 1 square inch of free

area per 2,000 BTUH (1,1 cm

2

/kW) of combined input

for all gas appliances in the space

(

see

Table 1)

.

359AA

V

Summary of Contents for 4-WAY MULTIPOISE 359AAV

Page 1: ...sulted before installation to determine the need to obtain a permit IPEX System 636 is a trademark of IPEX Inc CONSIGNES SP CIALES POUR L IN STALLATION DE VENTILLATION AU CANADA L installation faite a...

Page 2: ...or of the building at a minimum height of eight 8 feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment The sign shall...

Page 3: ...h unit and other safety precautions that may apply These instructions cover the minimum requirements and conform to existing national standards and safety codes In some instances these instructions ex...

Page 4: ...ldings or structures under construction S This furnace is NOT approved for installation in mobile homes trailers or recreation vehicles S Seal around supply and return air ducts S Install correct filt...

Page 5: ...to the plastic Transition box Squeeze the hose together near the end and quickly reconnect the 3 4 19 mm OD rubber hose to the stub on the condensate trap Secure with the hose clamp When you return ho...

Page 6: ...the floor S Located or physically protected from possible damage by a vehicle 10 Local codes may require a drain pan under the entire furnace and condensate trap when the furnace is installed in atti...

Page 7: ...For venting information literature contact www Bryant com with the complete model and serial number of the furnace On the Dual Certified furnace the vent and combustion air pipes attach to the furnace...

Page 8: ...2 122 2 27 318 177 5 609 6 30 2 249 2 177 8 31 7 73 549 3 27 109 5 122 2 758 8 690 6 549 3 855 7 439 7 42 9 123 8 177 8 47 6 469 9 723 9 57 2 336 6 60 3 27 1016 19 1 587 4 98 4 Specifications are subj...

Page 9: ...t or masonry chimney Multistory venting is NOT permitted If this furnace is replacing a previously common vented furnace it may be necessary to resize the existing vent and chimney to prevent oversizi...

Page 10: ...322 cm2 33 3 sq in 215 cm2 25 sq in 161 cm2 6 152 mm EXAMPLE Determining Free Area Furnace 100 000 Furnace 100 000 Water Heater 30 000 Water Heater 30 000 Total Input 130 000 4 000 Total Input 130 000...

Page 11: ...idered as communicating spaces where such spaces are connected by one or more openings in doors or floors having a total minimum free area of 2 in 2 1 000 BTUH 4 400 mm2 kW of total input rating of al...

Page 12: ...ce can NOT be common vented or connected to any type B BW or L vent or vent connector nor to any portion of a factory built or masonry chimney If this furnace is replacing a previously common vented f...

Page 13: ...12 The minimum pipe run length is 2 6 M 13 The piping can be run in the same chase or adjacent to supply or vent pipe for water supply or waste plumbing It can also be run in the same chase with a ven...

Page 14: ...are required the length can be INCREASED by 5 1 5 M for each additional elbow NOT used NOTE It is allowable to use larger diameter pipe and fitting than shown in the tables but not smaller diameters t...

Page 15: ...15 12 inches 30 cm for applieances 10 000 Btuh 3 kW and 100 000 Btuh 30kW 36 inches 91cm for appliances 100 000 Btuh 30kW A06675 Fig 7 Direct Vent Termination Clearance 359AAV...

Page 16: ...16 Fig 8 Other than Direct Vent Termination Clearance 359AAV...

Page 17: ...remain in the furnace between the door switch plate and the blower shelf Fig 9 during operation See Fig 19 for proper routing and installation of the overflow DO NOT trap the drain line in any other l...

Page 18: ...rommet in loose parts bag S Install the 1 2 13 mm CPVC street elbow on discharge of trap S Install the black PVC tube connector 3 4 18 mm PVC x 1 2 13 mm CPVC from loose parts bag as shown in the illu...

Page 19: ...of 2 51 mm PVC pipe long enough to exit the cabinet and connect the vent drain to either A standard field supplied 2 51 mm PVC tee or A 2 PVC coupling fastened onto the drain tee S Install tee trap in...

Page 20: ...the vent drain to the trap Secure all connections with clamps S Install the vent pipe grommet into the casing S Cut an appropriate length of 2 51 mm PVC pipe long enough to exit the cabinet and conne...

Page 21: ...to the left side of the unit using the two 2 screws provided Cut the 5 8 16 mm ID corrugated hose as shown above and fasten the 90 bend end to the trap and fasten the straight end to the transition dr...

Page 22: ...o the top of the trap and mount the trap externally to the right side of the unit using the two 2 screws provided Connect the corrugated drain tube from the transition box to the trap as shown If an e...

Page 23: ...he 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrugated hose from the transition to the trap Secure connections with clamps S Rem...

Page 24: ...e will exit S Mount the trap externally to the bottom side of the unit using the 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrug...

Page 25: ...Mount the trap externally to the bottom side of the unit using the 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrugated hose from...

Page 26: ...will exit S Mount the trap externally to the bottom side of the unit using the 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrugat...

Page 27: ...ig 18 that corresponds to the installation position of the furnace for the application Preassemble the vent and combustion air piping from the furnace to the vent termination Do not cement the pipe jo...

Page 28: ...til it bottoms out NOTE Cement MUST be fluid while inserting pipe If NOT recoat pipe 4 Hold the pipe in the fitting for 30 seconds to prevent the tapered socket from pushing the pipe out of the fittin...

Page 29: ...ng materials may be affected by flue products expelled in close proximity to unprotected surfaces Sealing or shielding of the exposed surfaces with a corrosion resistant material such as aluminum shee...

Page 30: ...Snow Level 36 Min 2 50 8mm Max 36 Min OR 914 4mm 914 4mm A07718 Fig 25 Concentric Vent and Combustion Air Roof Termination A Vent Dimension A is touching or 2 in 503 8mm maximum separation 25 22 02d...

Page 31: ...he installation from Table 4 and Fig 32 2 Determine the best location for the termination kit See Fig 31 for vertical termination or Fig 35 for horizontal termination Roof termination is preferred sin...

Page 32: ...Airflow restriction will occur and the furnace pressure switch may cause intermittent operation Drill clearance hole in rain cap and pilot hole in vent pipe Stainless steel screw Field supplied A07722...

Page 33: ...essures Combustion Air Vent Combustion Air Vent 45 Elbow Field Supplied 25 22 02 Strap Field Supplied Flush to 1 25 4mm max Note Securing strap must be field installed to prevent movement of termina t...

Page 34: ...in National Fuel Gas Code or CGA codes 3 Two stage regulation of Propane gas is recommended Propane Conversion FIRE EXPLOSION HAZARD Failure to follow this warning could result in personal injury or d...

Page 35: ...2 pressure switches Manual shut off valve Alternative installation Representative drawing only some models may vary in appearance A07724 Fig 36 Typical Gas Piping for Upflow Use elbows and 3 76 mm pip...

Page 36: ...s 6 and 7 Table 7 LPG or Propane Gas Manifold Pressure in wc HEATING VALUE BTU CU FT FURNACE INPUT BTU BURNER MEAN ELEVATION FEET ABOVE SEA LEVEL Ft M 0 to 2000 2001 to 3000 3001 to 4000 4001 to 5000...

Page 37: ...injury and or loss of life WARNING 1 The furnace and the equipment shut off valve must be dis connected from the gas supply piping system during any pressure testing of that system at test pressures...

Page 38: ...e 115V HUM called HUM on Control is energized when the inducer is energized ELECTRONIC AIR CLEANER EAC is energized when there is a blower speed call except is NOT energized when blower operates in th...

Page 39: ...ucts under the floor or through the attic 1 For side connections using a 16 x 25 406 x 635 mm filter cut out the embossed area shown in Fig 41 This will provide a 141 2 x 221 2 368 x 572 mm approxim a...

Page 40: ...unit to avoid condensation on the heat exchanger All furnaces are designed with a break away duct flange on the supply air side of the furnace This allows for installation in the horizontal right or...

Page 41: ...tent 1 Turn OFF gas supply to all appliances and start furnace Use jumper wire on R to W for Heat 2 Time how many seconds it takes the smallest dial on the gas meter to make one complete revolution Re...

Page 42: ...inal will not be available at the Unused Motor Lead location Continuous Fan Operation using G Energizing the G terminal on the furnace control provides continuous fan operation This is done by connect...

Page 43: ...lve is energized the main burners light and flame is sensed S The igniter is de energized after the main burners ignite S FCB will delay blower operation for the 30 seconds timed from the opening of t...

Page 44: ...ger than two minutes 1 hr delay roll out switch requires manual reset 8 Flashes Permanent Lockout Gas valve relay contact stuck closed or miswired gas valve power reset only 10 Flashes Line voltage 11...

Reviews: