background image

27

before operation.

Verify all condensate drain connections are

securely clamped. A coupling and clamps (in loose part bag) may
be installed as shown for future servicing of the vent system.

Open Tee

Tee Trap

Condensate
Trap

Evaporator

Coil

Drain Line
(Optional)

Main
Drain
Line

INLE

T

EXH

A

U

ST

IN

ON

OFF

VENT

Representative drawing only, some models may vary in appearance.

A07713

Fig. 19 -- Connecting Tee Trap to Condensate Trap and Main

Drain Line

The tee trap must be connected to the main condensate drain line

as conceptually shown above. Different installations may require

slightly different orientations. The following steps apply to all

installations.

1. The tee trap should be installed as close to the side or top

of the furnace as practical. Minimize the distance between

the inducer and the tee trap as much as possible.

2. An open tee is to be used at the tee trap discharge. The top

end of the tee should be open to the atmosphere to elimin-

ate potential air lock problems.

3. The drain line from the tee trap is to be connected to the

furnace condensate trap drain line as shown above.

4. Condensate drain lines from a cooling coil may be connec-

ted downstream of the connection point of the tee trap and

furnace condensate trap.

IMPORTANT

:

Prime both traps with water before operation.

Failure to prime the traps may result in discharge of flue gases
from the condensate drain line and open tee for a period of time,
and may result in temporary lockout of the furnace upon start up.
Main drain line construction is left to the discretion of the
installer. It may be made of either rigid pipe or flexible tube.
Tube ID should NOT be less than

1

/

2

.

Connecting Vent and Combustion Air Piping

CARBON MONOXIDE POISONING HAZARD

Failure to follow this warning could result in personal injury or

death.
Cement or mechanically seal all joints, fittings, etc. to prevent

leakage of flue gasses.

!

WARNING

Refer to Fig. 10 through Fig. 18 that corresponds to the

installation position of the furnace for the application.
Preassemble the vent and combustion air piping from the furnace

to the vent termination. Do not cement the pipe joints until the

pipe preassembly process is complete.

Combustion Air Pipe Connection (

Dual Certified or

Direct Vent)

Install the air intake coupling and gasket to the furnace with the

four(4) screws:

NOTE

: The air intake coupling and gasket can be installed to the

top panel, or to the alternate air intake locations on either the left
or right side panels of the furnace.
For downflow installation, the air intake coupling and gasket

must be installed to the alternate air intake location on either the

left or right side panels. Remove the 3” (76 mm) hole plug from

the furnace accessory bag and relocate to the open hole in the

furnace panel. Use four screws to seal the four mounting holes in

the top panel next to the hole plug. Drill four 7/64” (3 mm)

diameter holes in the casing using the air intake coupling as the

template.
The air intake coupling is sized for 2

(51 mm) PVC pipe.

Install the combustion air pipe to the air intake coupling using

RTV sealant to provide for future serviceability.

Vent Pipe Connection

Install the vent pipe grommet to the furnace panel. Locate the

grommet in the furnace panel at a location directly away from the

vent fitting on the combustion blower. The grommet snaps into

the 3

(76 mm) hole on the furnace panel. NOTE: Depending on

the installation position, the vent pipe grommet will be installed

to the top panel or to the alternate location on the side panels. If

needed, remove the 3

(76 mm) hole plug from the loose parts

bag and relocate to the open hole in the furnace panel. (See Fig.

10 or Fig. 19.)
Install the vent pipe to the rubber coupling, the vent fitting or the

PVC vent extension pipe. Securely attach using the clamp or

PVC cement as required.

NOTE: The vent fitting MUST be installed with the air flow
marking arrow pointed toward the vent pipe. (See Fig. 20.)
Some installations require the vent fitting to be installed with
a 5

°

to 10

°

downward slope. (See Fig. 10 through Fig. 19.)

359AA

V

Summary of Contents for 4-WAY MULTIPOISE 359AAV

Page 1: ...sulted before installation to determine the need to obtain a permit IPEX System 636 is a trademark of IPEX Inc CONSIGNES SP CIALES POUR L IN STALLATION DE VENTILLATION AU CANADA L installation faite a...

Page 2: ...or of the building at a minimum height of eight 8 feet above grade directly in line with the exhaust vent terminal for the horizontally vented gas fueled heating appliance or equipment The sign shall...

Page 3: ...h unit and other safety precautions that may apply These instructions cover the minimum requirements and conform to existing national standards and safety codes In some instances these instructions ex...

Page 4: ...ldings or structures under construction S This furnace is NOT approved for installation in mobile homes trailers or recreation vehicles S Seal around supply and return air ducts S Install correct filt...

Page 5: ...to the plastic Transition box Squeeze the hose together near the end and quickly reconnect the 3 4 19 mm OD rubber hose to the stub on the condensate trap Secure with the hose clamp When you return ho...

Page 6: ...the floor S Located or physically protected from possible damage by a vehicle 10 Local codes may require a drain pan under the entire furnace and condensate trap when the furnace is installed in atti...

Page 7: ...For venting information literature contact www Bryant com with the complete model and serial number of the furnace On the Dual Certified furnace the vent and combustion air pipes attach to the furnace...

Page 8: ...2 122 2 27 318 177 5 609 6 30 2 249 2 177 8 31 7 73 549 3 27 109 5 122 2 758 8 690 6 549 3 855 7 439 7 42 9 123 8 177 8 47 6 469 9 723 9 57 2 336 6 60 3 27 1016 19 1 587 4 98 4 Specifications are subj...

Page 9: ...t or masonry chimney Multistory venting is NOT permitted If this furnace is replacing a previously common vented furnace it may be necessary to resize the existing vent and chimney to prevent oversizi...

Page 10: ...322 cm2 33 3 sq in 215 cm2 25 sq in 161 cm2 6 152 mm EXAMPLE Determining Free Area Furnace 100 000 Furnace 100 000 Water Heater 30 000 Water Heater 30 000 Total Input 130 000 4 000 Total Input 130 000...

Page 11: ...idered as communicating spaces where such spaces are connected by one or more openings in doors or floors having a total minimum free area of 2 in 2 1 000 BTUH 4 400 mm2 kW of total input rating of al...

Page 12: ...ce can NOT be common vented or connected to any type B BW or L vent or vent connector nor to any portion of a factory built or masonry chimney If this furnace is replacing a previously common vented f...

Page 13: ...12 The minimum pipe run length is 2 6 M 13 The piping can be run in the same chase or adjacent to supply or vent pipe for water supply or waste plumbing It can also be run in the same chase with a ven...

Page 14: ...are required the length can be INCREASED by 5 1 5 M for each additional elbow NOT used NOTE It is allowable to use larger diameter pipe and fitting than shown in the tables but not smaller diameters t...

Page 15: ...15 12 inches 30 cm for applieances 10 000 Btuh 3 kW and 100 000 Btuh 30kW 36 inches 91cm for appliances 100 000 Btuh 30kW A06675 Fig 7 Direct Vent Termination Clearance 359AAV...

Page 16: ...16 Fig 8 Other than Direct Vent Termination Clearance 359AAV...

Page 17: ...remain in the furnace between the door switch plate and the blower shelf Fig 9 during operation See Fig 19 for proper routing and installation of the overflow DO NOT trap the drain line in any other l...

Page 18: ...rommet in loose parts bag S Install the 1 2 13 mm CPVC street elbow on discharge of trap S Install the black PVC tube connector 3 4 18 mm PVC x 1 2 13 mm CPVC from loose parts bag as shown in the illu...

Page 19: ...of 2 51 mm PVC pipe long enough to exit the cabinet and connect the vent drain to either A standard field supplied 2 51 mm PVC tee or A 2 PVC coupling fastened onto the drain tee S Install tee trap in...

Page 20: ...the vent drain to the trap Secure all connections with clamps S Install the vent pipe grommet into the casing S Cut an appropriate length of 2 51 mm PVC pipe long enough to exit the cabinet and conne...

Page 21: ...to the left side of the unit using the two 2 screws provided Cut the 5 8 16 mm ID corrugated hose as shown above and fasten the 90 bend end to the trap and fasten the straight end to the transition dr...

Page 22: ...o the top of the trap and mount the trap externally to the right side of the unit using the two 2 screws provided Connect the corrugated drain tube from the transition box to the trap as shown If an e...

Page 23: ...he 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrugated hose from the transition to the trap Secure connections with clamps S Rem...

Page 24: ...e will exit S Mount the trap externally to the bottom side of the unit using the 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrug...

Page 25: ...Mount the trap externally to the bottom side of the unit using the 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrugated hose from...

Page 26: ...will exit S Mount the trap externally to the bottom side of the unit using the 2 screws provided in the location shown S Cut the corrugated tube as shown in the illustration above Connect the corrugat...

Page 27: ...ig 18 that corresponds to the installation position of the furnace for the application Preassemble the vent and combustion air piping from the furnace to the vent termination Do not cement the pipe jo...

Page 28: ...til it bottoms out NOTE Cement MUST be fluid while inserting pipe If NOT recoat pipe 4 Hold the pipe in the fitting for 30 seconds to prevent the tapered socket from pushing the pipe out of the fittin...

Page 29: ...ng materials may be affected by flue products expelled in close proximity to unprotected surfaces Sealing or shielding of the exposed surfaces with a corrosion resistant material such as aluminum shee...

Page 30: ...Snow Level 36 Min 2 50 8mm Max 36 Min OR 914 4mm 914 4mm A07718 Fig 25 Concentric Vent and Combustion Air Roof Termination A Vent Dimension A is touching or 2 in 503 8mm maximum separation 25 22 02d...

Page 31: ...he installation from Table 4 and Fig 32 2 Determine the best location for the termination kit See Fig 31 for vertical termination or Fig 35 for horizontal termination Roof termination is preferred sin...

Page 32: ...Airflow restriction will occur and the furnace pressure switch may cause intermittent operation Drill clearance hole in rain cap and pilot hole in vent pipe Stainless steel screw Field supplied A07722...

Page 33: ...essures Combustion Air Vent Combustion Air Vent 45 Elbow Field Supplied 25 22 02 Strap Field Supplied Flush to 1 25 4mm max Note Securing strap must be field installed to prevent movement of termina t...

Page 34: ...in National Fuel Gas Code or CGA codes 3 Two stage regulation of Propane gas is recommended Propane Conversion FIRE EXPLOSION HAZARD Failure to follow this warning could result in personal injury or d...

Page 35: ...2 pressure switches Manual shut off valve Alternative installation Representative drawing only some models may vary in appearance A07724 Fig 36 Typical Gas Piping for Upflow Use elbows and 3 76 mm pip...

Page 36: ...s 6 and 7 Table 7 LPG or Propane Gas Manifold Pressure in wc HEATING VALUE BTU CU FT FURNACE INPUT BTU BURNER MEAN ELEVATION FEET ABOVE SEA LEVEL Ft M 0 to 2000 2001 to 3000 3001 to 4000 4001 to 5000...

Page 37: ...injury and or loss of life WARNING 1 The furnace and the equipment shut off valve must be dis connected from the gas supply piping system during any pressure testing of that system at test pressures...

Page 38: ...e 115V HUM called HUM on Control is energized when the inducer is energized ELECTRONIC AIR CLEANER EAC is energized when there is a blower speed call except is NOT energized when blower operates in th...

Page 39: ...ucts under the floor or through the attic 1 For side connections using a 16 x 25 406 x 635 mm filter cut out the embossed area shown in Fig 41 This will provide a 141 2 x 221 2 368 x 572 mm approxim a...

Page 40: ...unit to avoid condensation on the heat exchanger All furnaces are designed with a break away duct flange on the supply air side of the furnace This allows for installation in the horizontal right or...

Page 41: ...tent 1 Turn OFF gas supply to all appliances and start furnace Use jumper wire on R to W for Heat 2 Time how many seconds it takes the smallest dial on the gas meter to make one complete revolution Re...

Page 42: ...inal will not be available at the Unused Motor Lead location Continuous Fan Operation using G Energizing the G terminal on the furnace control provides continuous fan operation This is done by connect...

Page 43: ...lve is energized the main burners light and flame is sensed S The igniter is de energized after the main burners ignite S FCB will delay blower operation for the 30 seconds timed from the opening of t...

Page 44: ...ger than two minutes 1 hr delay roll out switch requires manual reset 8 Flashes Permanent Lockout Gas valve relay contact stuck closed or miswired gas valve power reset only 10 Flashes Line voltage 11...