5. Commissioning
5.1
Before switching on
Opening the transparent front panel cover: Using the arrow
on the bottom left-hand corner of the panel cover as a
reference, lift the panel cover in an upward direction. The
cover can also be removed completely. Refit the front panel
cover as soon as the adjustments are completed.
1. Does the connected supply voltage
U
S
match the informa-
tion on the nameplate?
2. Only when busbar systems are used: Has the maximum
permissible nominal insulation voltage of the measuring
current transformers been observed?
3. Are you sure that the PE conductor has not been routed
through the measuring current transformer at any point?
4. In mounting the measuring current transformers, have any
magnetic fields that are nearby and could cause interference
been taken into account?
5. Has the maximum permissible cable length for the meas-
uring current transformers been observed?
6. Is a 120 Ω resistor connected at the beginning and end of
the BMS bus?
7. Have the maximum permissible interface cable length
(1200 m) and number of BMS bus nodes (32) been
observed?
8. In respect of the BMS bus node address settings, has each
address only been assigned once? Is address 001 and
therefore the master function, assigned?
Summary of Contents for LANTRAXX CMS460-D
Page 6: ......
Page 21: ...Installation and connection 21 CMS460 D_D00045_01_M_XXEN 07 2016 4 3 2 Wiring diagram ...
Page 26: ...Installation and connection 26 CMS460 D_D00045_01_M_XXEN 07 2016 ...
Page 28: ...Installation and connection 28 CMS460 D_D00045_01_M_XXEN 07 2016 ...
Page 66: ...Operation 66 CMS460 D_D00045_01_M_XXEN 07 2016 ...
Page 70: ...Tests service troubleshooting 70 CMS460 D_D00045_01_M_XXEN 07 2016 ...
Page 85: ......
Page 86: ......
Page 87: ......