(x 40) 1" GALVANIZED ROOFING NAILS
PARTS REQUIRED:
DORMER FLASHING / SHINGLES
Trim, bend and nail a 5" x 7" flashing at the dormer corner
(Fig. B)
. Secure flashing with 1" nails.
Lay first row of shingles on top of flashing
(Fig. C)
. Secure shingles with 1" nails. Lay second row of shingles up to
side of dormer
(Fig. C)
. Secure with 1" nails. Bend, place and nail a 5" x 7" flashing up the dormer wall and on top
of shingle. Overlap first 5" x 7" flashing by 2". Secure with 1" nails.
Do not nail into dormer wall.
Lay next shingle on top of 5" x 7" flashing. Secure shingle with 1" nails. Bend and place next 5" x 7" flashing up
the dormer wall and on top of shingle. Overlap flashing by 2". Secure flashing with 1" nails.
Keep alternating and stepping flashing and shingles as in
Step 5 until you have reached the roof peak
(Fig. D)
.
You will have to trim flashing when you work near top of dormer.
(x 30) 5" x 7" Aluminum Flashing Cards
Repeat Steps 4-6 for opposite side.
You have finished installing your dormer flashing. Proceed to complete your dormer.
FINISH