ATEX Retractor System TANKO-RT/-RTS
88/121
Translation - Operating/installation instructions 2020/01
7 Maintenance
Material
Blind plug for combination container connector, article number
1.4435
66R0000004Z30
2.4602
66R0000004Z80
BioControl
®
process connection
1.
Check the following before pulling the device out of the container:
–
Device in “rest position”, i.e. spray head in hydraulic pipe
–
Check for interfering contours on surrounding components in the container.
2.
The device must be supported/held securely in place during removal.
3.
Undo the additional fastenings on the retractor system.
4.
Undo the block flange and set it to one side.
5.
Remove the device from the block flange on the container.
6.
Keep the gasket in a safe place.
7.
Seal the process connection using a suitable screw cap.
8.
If necessary, close the block flange on the container.
To close off the block flange, a BioControl
®
blanking plate can be obtained from NEUMO.
Weld Process Connection
9.
Check the following before pulling the device out of the container:
–
Device in “rest position”, i.e. spray head in hydraulic pipe
–
Check for interfering contours on surrounding components in the container.
10.
The device must be supported/held securely in place during removal.
11.
Undo the additional fastenings on the retractor system.
12.
Undo the heavy duty clamp at the connection between the hydraulic pipe and the pneumatic pipe
and set aside.
13.
Carefully remove the pneumatic pipe from the hydraulic pipe. The piston rod with centering adapter,
spray head and all attachments is held in place by the locking cylinder on the pneumatic pipe and is
also pulled out of the hydraulic pipe.
14.
Close off the hydraulic pipe with blind clamp connector 2 1/2" DIN 32676.