Translation of original operating instructions
86
AL-KO AT4F ATEX
CAUTION
Risk of fire and explosion due to foreign objects on the electric heating coil
Before commissioning, check the electric heating coil for foreign objects.
ATTENTION
Hygienic and toxological concerns may arise during 100% recirculation air operation due to
the contamination of the waste air with pollutant gases. A minimum outdoor air volume flow
must therefore be ensured during recirculation air operation.
ATTENTION
Check seals before commissioning and apply seals when fans are running.
Before starting up the system, check:
Mechanical function of the multi-leaf dampers.
Tight fit of all installed filters.
NOTE
AL-KO THERM generally recommends the replacement of all installed filters after a short
period of operation of the AC unit to remove any dirt that may have entered the filters during
the installation phase and after commissioning (see chapter "7.4 Replacing components" on
page 126).
Use only original spare parts.
Customer Service
Phone: +49 8225 39 - 2574
E-mail: [email protected]
Web: www.al-ko.com
Bypass damper for mechanical function (plate heat exchanger).
Fan for foreign objects and easy running.
Heat exchangers for contamination, damage and leakage of the media connections.
Each condensate drain must be connected to the drain system by a separate siphon. Direct connection of water
drains to the drain system is not permitted.
Fully assemble the unit and commission it according to the commissioning protocol.
Inspection doors/inspection covers must be closed.
The inspection covers must be integrated into the unit potential. After each release of these connections, they must
be restored, checked and documented.
Summary of Contents for AT4F Series
Page 138: ...Translation of original operating instructions 138 AL KO AT4F ATEX Notes...
Page 139: ......