Installation - 8
10.
Verify that the system is level
— Adjust pads as
required. This is done by turning the top of the
threaded shaft (
).
Figure 4
Loader Height Setup
ADVICE
If the 5DX system is to be integrated into a production line,
you
may wish to level and adjust height at the same time,
after the loaders are installed.
Floor Level
Height of Loader
Belt (top) Above
Spacers
“Fixed” Loader Rail
Adjusting Loader Rail
Spacers
Foot with
threaded shaft
C spacer
A spacer
B spacer
CHECK THE HEIGHT OF
BOTH RAILS OF BOTH
LOADERS
Floor