Figure2-14: Schematic – System Pump Start using a Separate Contact Relay
Figure 2-15: Identifying the Presence of BMK Pump Relay Option 69102
2.15 SEQUENCING ISOLATION VALVE INSTALLATION
All Benchmark units are shipped with a connection for an optional motorized
external
sequencing isolation valve (p/n 92084-TAB) included in the shipping container. This valve is an
integral component of the AERCO’s on-board Boiler Sequencing Technology (BST) solution.
BST allows sites with multiple boilers to have one boiler, acting as a “master” to manage the
other boilers at the site in such a way that the efficiency of the entire boiler array is maximized.
When operated with the BST system, the Master controls its own isolation valve and sends
signals to the slave units to open or close their isolation valves. After the boiler load is satisfied,