Gen II
User Manual
10-28 – Fan/Turbine Balance
Chapter 10
Revision 2.10, Apr 2020
10.1.15.
– Start Aircraft
10.1.15.1.
The screen will again display the Start Aircraft banner screen and indicate a new
Run number. From this point, repeat steps 10.1.11 to 10.1.14 above until the
vibration amplitude is reduced to an acceptable level or below the target
amplitude entered in the setup.
10.1.15.2.
When the vibration levels have been reduced to a level equal to or lower than the
target value set in paragraph 10.1.6.13 above, the “Balance Status” screen will be
displayed. It informs you that the target value has been met and gives you the
option to press [F1] “Quit Job” or [F5] “Continue” to continue the balance
process. Pressing [F1] will complete the job and store any pertinent information
back into the setup. If the job went well, the Influence Coefficient (ICF) stored in
the setup will be updated.