The switching to available source can be
summarized in the following steps:
1. An anomaly occurs on SOURCE 1
2. Override momentary S1 outage delay
3. Pre-transfer signal on
4. Pre-transfer S1 to S2 delay
5. Transfer switch (SOURCE 1) to
position O
6. Center-off delay (only with Delayed
transition I - O - II type)
7. Transfer switch (SOURCE 2) to
position II
8. Post-transfer S1 to S2 delay
9. Pre-transfer signal off
When an anomaly occurs in the source in-
use, the re-transfer to available source
can be summarized in the following steps:
1. SOURCE 1 is restored
2. An anomaly occurs on the SOURCE 2
3. Pre-
transfer signal on
4. Pre-transfer S2 to S1 delay
5. Transfer switch (SOURCE 2) to
position O
6. Center-off delay (only with Delayed
transition I - O - II type)
7. Transfer switch (SOURCE 1) to
position I
8. Post-transfer S2 to S1 delay
9. Pre-transfer signal off
2.5.1.3 No Source Priority (Generator
and load shed usage disabled)
Summary of Contents for Zenith ZTS T Series
Page 2: ...2 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 6: ...6 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 10: ...10 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 36: ...36 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 44: ...44 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 106: ...106 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 108: ...108 1 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 122: ...2 122 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 126: ...2 126 ZENITH ZTS D T SERIES 1600 3000 A ZTSCT T SERIES 100 3000 A ...
Page 129: ...129 1 OPER ATION MAINTENANCE AND INSTALL ATION GUIDE ...