Installation and commissioning guide
1ZSC000562-AAK EN, REV. 2, 2019-07-03
29
5 Drying
5.1 Preparations
Procedure
1.
Remove the bolts (2), and then the top cover (1).
CAUTION!
Carefully lift the top cover straight up.
The shaft for the bevel gear can bend if
the top cover is not lifted straight up.
CAUTION!
Do not drop bolts or other small parts
into the tap-changer.
Objects that fall into the tap-changer
can prevent the free movement of the
mechanism, or cause electrical short
circuits.
G004481
2.
Remove the O-ring (3).
G004284
3.
Put the parts in storage in a dry and dust-free area.
End of instruction
Summary of Contents for VUBB
Page 14: ...14 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 28: ...28 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 52: ...52 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 60: ...60 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 68: ...68 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 72: ...72 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 74: ...74 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...
Page 76: ...76 Installation and commissioning guide 1ZSC000562 AAK EN REV 2 2019 07 03 ...