Section 5
Establishing connection and
verifying the IEC 61850 station
communication
5.1
Setting the station communication
SEMOD172108-3 v7
To enable IEC 61850 station communication:
•
The IEC 61850-8-1 station communication functionality must be on in the local HMI.
Navigate to Main menu/Configuration/Communication/Station communication/
IEC61850-8-1:1 and set the
Operation parameter to On.
•
To enable GOOSE communication the
Operation parameter for the corresponding GOOSE
function blocks (GOOSEBINRCV and GOOSEINTLKRCV) must be set to
On in the
application configuration.
•
To enable GOOSE communication via the front port the parameter
PortSelGOOSE in Main
menu/Configuration/Communication/Station communication/IEC61850-8-1:1 must be
set to
Front. To enable GOOSE communication via rear port the parameter PortSelGOOSE
must be set to
LAN1.
•
To enable MMS communication via the rear port the parameter
PortSelMMS in Main
menu/Configuration/Communication/Station communication/IEC61850-8-1:1 must be
set to
LAN1.
5.2
Verifying the station communication
SEMOD172108-24 v7
Connect your PC to the substation network and ping the connected IED and the Substation
Master PC, to verify that the communication is working (up to the transport layer).
The best way to verify the communication up to the application layer is to use protocol
analyzer connected to the substation bus, and monitor the communication.
1MRK 505 293-UEN B
Section 5
Establishing connection and verifying the IEC 61850 station communication
Breaker protection REQ650
35
Commissioning manual
© Copyright 2013 ABB. All rights reserved
Summary of Contents for REQ650 1.3 IEC
Page 1: ...Relion 650 SERIES Breaker protection REQ650 Version 1 3 IEC Commissioning manual ...
Page 2: ......
Page 12: ...6 ...
Page 20: ...14 ...
Page 28: ...22 ...
Page 40: ...34 ...
Page 42: ...36 ...
Page 116: ...110 ...
Page 123: ...117 ...