Installing the IED
1
Overview
The mechanical and electrical environmental conditions at the installation site must be within
the limits described in the IED technical data. Dusty, damp places, places susceptible to rapid
temperature variations, powerful vibrations and shocks, surge voltages of high amplitude and
fast rise time, strong induced magnetic fields or similar extreme conditions should be avoided.
Sufficient space must be available in front of and at the rear of the IED to allow access for main-
tenance and future modifications. Flush mounted IEDs should be mounted so that IED modules
can be added and replaced without excessive dismantling.
Summary of Contents for RELION REL670
Page 8: ...Contents ...
Page 72: ...64 About this chapter Chapter 9 Establishing connection and verifying the LON communication ...
Page 174: ...166 Remote communication Chapter 11 Verifying settings by secondary injection ...
Page 190: ...182 Maintenance Chapter 13 Fault tracing and repair ...
Page 198: ...190 Glossary Chapter 14 Glossary ...