3
Introduction to the installation and
commissioning manual
Chapter 1
Introduction
•
The chapter
“Unpacking and checking the IED”
explains how to take delivery of
the IED.
•
The chapter
“Installing the IED”
explains how to install the IED.
•
The chapter
“Checking the external optical and electrical connections”
explains
how to check that the IED is properly connected to the protection system.
•
The chapter
“Energizing the IED”
explains how to start the IED.
•
The chapter contains explains how to enter SPA/IEC settings and verifying the
SPA/IEC communication.
•
The chapter
“Establishing connection and verifying the LON communication”
contains a reference to another document.
•
The chapter
“Configuring the IED and changing settings
” explains how to down-
load settings and configure the terminal.
•
The chapter
“Verifying settings by secondary injection”
contains instructions on
how to verify that each included function operates correctly according to the set
values.
•
The chapter
“Commissioning and maintenance of the fault clearing system
” dis-
cusses maintenance tests and other periodic maintenance measures.
•
The chapter
“Fault tracing and repair”
explains how to troubleshoot.
•
The chapter
“Glossary”
is a list of terms, acronyms and abbreviations used in
ABB technical documentation.
1.3
Intended audience
1.3.1
General
The installation and commissioning manual addresses the personnel responsible for the installa-
tion, commissioning, maintenance and taking the protection in and out of normal service.
1.3.2
Requirements
The installation and commissioning personnel must have a basic knowledge in handling elec-
tronic equipment. The commissioning and maintenance personnel must be well experienced in
using protection equipment, test equipment, protection functions and the configured functional
logics in the protection.
1.4
Related documents
Documents related to REL670
Identity number
Operator’s manual
1MRK 505 233-UEN
Installation and commissioning manual
1MRK 506 234-UEN
Technical reference manual
1MRK 506 232-UEN
Application manual
1MRK 505 235-UEN
Buyer’s guide
1MRK 506 264-BEN
Connection diagram, Single breaker arr. Three phase tripping arr.
1MRK 002 801-BA
Connection diagram, Single breaker arr. Single phase tripping arr.
1MRK 002 801-CA
Connection diagram, Multi breaker arr. Three phase tripping arr.
1MRK 002 801-DA
Summary of Contents for RELION REL670
Page 8: ...Contents ...
Page 72: ...64 About this chapter Chapter 9 Establishing connection and verifying the LON communication ...
Page 174: ...166 Remote communication Chapter 11 Verifying settings by secondary injection ...
Page 190: ...182 Maintenance Chapter 13 Fault tracing and repair ...
Page 198: ...190 Glossary Chapter 14 Glossary ...