Start-up 79
First start assistance appears automatically to
the screen if the inverter has been powered up
for the first time after factory tests. First start
assistance also appears automatically if the
unit has been powered up but the first start-up
settings have not been confirmed by the user.
Press right softkey to continue forward.
Set the date with the Up or Down Arrow keys.
Use the Right or Left Arrow keys to move
between the Day, Month and Year.
Press the right softkey to Save the date and to
proceed forward.
The date appears on the upper right part of the
status bar.
Set the time with the Up or Down Arrow keys.
Use the Right or Left Arrow keys to move
between the Hours, Minutes and Seconds.
Press the right softkey to Save the time
selections and to proceed forward.
First start-up
Summary of Contents for PVS300
Page 1: ...ABB solar inverters Product manual PVS300 string inverters ...
Page 4: ......
Page 9: ...Table of contents 9 Further information ...
Page 10: ...10 Table of contents ...
Page 34: ...34 Operation basics and hardware description ...
Page 48: ...48 Planning the installation ...
Page 76: ...76 Installation checklist ...
Page 110: ...110 Troubleshooting ...
Page 120: ...120 Technical data ...
Page 122: ...122 Dimension drawing 3AUA0000094904 ...
Page 123: ...Dimension drawing 123 Required clearances for cooling ...
Page 124: ...124 Dimension drawing ...
Page 126: ...126 Navigation map The navigation map ...
Page 127: ...Navigation map 127 ...
Page 128: ...128 Navigation map ...
Page 130: ...3AUA0000096321 Rev B EN EFFECTIVE 2013 03 14 Contact us www abb com solar ...