Planning the installation 39
Selecting the control cables
General rules
It is recommended to use halogen free, shielded control and data cables.
A double-shielded cable is the best alternative for low-voltage digital signals but a
single-shielded twisted pair cable is also usable.
Signals in separate cables
Never mix 24 V DC and 115/230 V AC signals in the same cable.
Signals allowed to be run in the same cable
Relay-controlled signals can share the same cables as digital signals, provided that
their voltage does not exceed 48 V. It is recommended to run relay controlled signals
as twisted pairs.
Fieldbus and I2I link signals can share the same cable, provided that the Data +/-
signal conductors run in the same twisted pair and both interfaces have separate
functional ground conductors.
Recommended relay cable type
Cable type with a braided metallic screen (for example, Lapp Kabel ÖLFLEX or
equivalent) has been tested and approved by ABB.
Recommended cable type for Modbus over EIA/RS-485
Shielded twisted pair cable (STP), impedance 100...150 ohm with 120 ohm
termination resistors (for example, Lapp Kabel UNITRONIC
®
LiHCH (TP) or
equivalent) is recommended.
According to the RS-485 standard, 1200 m is the maximum cabling distance for data
transfer velocities under 100 kBits/s when termination resistors are used.
Double-shielded twisted pair cable
Single-shielded twisted pair cable
Summary of Contents for PVS300
Page 1: ...ABB solar inverters Product manual PVS300 string inverters ...
Page 4: ......
Page 9: ...Table of contents 9 Further information ...
Page 10: ...10 Table of contents ...
Page 34: ...34 Operation basics and hardware description ...
Page 48: ...48 Planning the installation ...
Page 76: ...76 Installation checklist ...
Page 110: ...110 Troubleshooting ...
Page 120: ...120 Technical data ...
Page 122: ...122 Dimension drawing 3AUA0000094904 ...
Page 123: ...Dimension drawing 123 Required clearances for cooling ...
Page 124: ...124 Dimension drawing ...
Page 126: ...126 Navigation map The navigation map ...
Page 127: ...Navigation map 127 ...
Page 128: ...128 Navigation map ...
Page 130: ...3AUA0000096321 Rev B EN EFFECTIVE 2013 03 14 Contact us www abb com solar ...