![ABB GOE(2) Installation And Commissioning Manual Download Page 38](http://html.mh-extra.com/html/abb/goe-2/goe-2_installation-and-commissioning-manual_5362038.webp)
38
Installation and commissioning guide
1ZSC000563-ACF EN, REV. A, 2020-06-25
8.
Pull down the upper draw rod (35) from the
bottom end of the bushing.
G006841
9.
Remove the transport cover (45) from the
transformer (46) and the lower draw rod (4).
G004681
10.
Lift the bushing to a position above the installation opening on the transformer.
End of instruction
4.6.2 Installation of the bushing on the transformer at site
Procedure
1.
Apply locking fluid on the threads (39) on the
lower draw rod (4).
CAUTION!
Make sure that all joints in the draw rod
are locked with thread-locking fluid.
NOTE!
Use thread-locking fluid grade 42 and
activator grade 47.