4.4 Installation with draw lead
4.4.1 Installation with draw lead
Overview
G002945
2
Draw lead
12 Pull-through cord
32 Inner terminal
33 Bushing
Procedure
1.
Braze the draw lead (2) from the transformer
windings to the inner terminal (32).