Mechanical installation
64
Connecting the liquid pipes
1. Ensure the Axilock connectors are slid on pipe ends. See section
on page
2. Position the liquid pipe ends against each other.
3. Centre the Axilock connector onto the pipe ends.
4. Tighten the connector bolts to a torque shown on the label attached to the
connector.
Connecting the PE busbars
Connect the PE busbars as shown below.
Parallel
misalignment:
max 3 mm (0.2”)
Angular error:
max 2° in any
direction
Axial gap: 5 to
15 mm (0.2” to
0.6”)
2
3
Tightening torque: 35–40 N·m (25–30 lbf·ft)
Strength class: 8.8
Spring washer
Plain washer
Plain washer
M10
Summary of Contents for ACS800-17LC
Page 1: ...ABB industrial drives Hardware manual ACS800 17LC Drives 55 to 5200 kW ...
Page 4: ......
Page 10: ...Update notice 6 ...
Page 18: ...Table of contents 12 ...
Page 26: ...Safety instructions 20 ...
Page 32: ...Introduction to the manual 26 ...
Page 60: ...Hardware description 54 ...
Page 74: ...Mechanical installation 68 ...
Page 114: ...Electrical installation 108 ...
Page 142: ...Maintenance 136 ...
Page 150: ...Internal cooling circuit 144 ...
Page 179: ...Dimensions 173 Frame sizes R7i R7i and R8i R8i bottom entry exit ...
Page 180: ...Dimensions 174 Frame sizes R7i R7i and R8i R8i marine units C121 ...
Page 182: ...www abb com drives www abb com drivespartners Contact us 3AUA0000065339 Rev B EN 2016 06 07 ...