20
T2300-T2350-T2400-T2450 Double Mitre Saw
4.7 PRELIMINARY CONTROLS
The Machine preliminary operations before the 1
st
starting, must be executed by a technician charged by the
customer. Before machine’s setting at work, it is necessary to execute certain verifications and checks to prevent
mistakes or accidents during setting at works step.
The verifications to be executed are the followings:
• Verify that machine has not been damaged during assembly step
• Verify with extreme care, the integrity of electric boards, control panels, electric cables, wires and pipes
• Check the proper connection of external power sources
• Connect the pedal to the machine
Because of the shipment, both blades and vertical clamps are lowered. To restore the normal position, operate
as follows:
• Turn clockwise the main switch (located on machine’s right side) on position 1 (see picture 4.7.1).
Picture 4.7.1
Picture 4.7.2
• Turn clockwise the vertical clamp cylinders switch (located under the main switch) on position 1 (see picture 4.7.2)
• Press simultaneously the two “A” push-buttons placed in front of working bench to lift up blades and vertical
clamps (see picture 4.7.3).
Picture 4.7.3
A
A
Summary of Contents for T2 Series
Page 3: ...3 Double Mitre Saw T2300 T2350 T2400 T2450...
Page 37: ...37 Double Mitre Saw T2300 T2350 T2400 T2450 ATTACHMENT A MACHINE OVERALL DIMENSIONS...
Page 38: ...38 T2300 T2350 T2400 T2450 Double Mitre Saw ATTACHMENT B MECHANIC SCHEMATICS PRELIMINARY...
Page 39: ...39 Double Mitre Saw T2300 T2350 T2400 T2450...
Page 40: ...40 T2300 T2350 T2400 T2450 Double Mitre Saw...
Page 41: ...41 Double Mitre Saw T2300 T2350 T2400 T2450...
Page 42: ...42 T2300 T2350 T2400 T2450 Double Mitre Saw...
Page 44: ...44 T2300 T2350 T2400 T2450 Double Mitre Saw ATTACHMENT D ELECTRIC SCHEMATICS...
Page 45: ...45 Double Mitre Saw T2300 T2350 T2400 T2450 ATTACHMENT E PLATES DISLOCATION PRELIMINARY...