2-1
2 Preparations
Summary
Describing the installation environment check.
Listing the installation tools.
Listing the technical documents needed for
installation.
2.1 Installation Environment Check
The items to check:
2.1.1 Checking Equipment Building Conditions
Check if the layout, height, bearing capability, shock-proof ability, doors and windows,
walls and troughs of the equipment building meet the requirements.
2.1.2 Checking Indoor Environment
Check the temperature, humidity, air pressure, ventilation condition, antistatic
protection measures, anti-interference measures, dustproof measures, rodent-resistant
measures, fire-protection facility, lighting condition, water supply and drainage system
of the equipment room.
To the highest priority, the equipment should be installed on the cool and dry walls
indoors with good ventilation; the fire-protection facility should be equipped; there
should be no caustic gas or smog in the room and no leakage on the roof; the
electromagnetic interference strength should be no more than 140dBµV/m
(0.01MHz~110000MHz). Or the equipment can be installed on the shady walls
outdoors with good ventilation and rain blocks. To the least priority, the equipment can
be installed on common walls, towers or high poles. The operating temperature range
of the equipment is between -40°C and +55°C, and the relative humidity range is
between 5% and 100%.
Содержание ZXCBTS M190T
Страница 1: ...ZXCBTS V5 4 CDMA Micro Base Transceiver Station RF Remote Station Installation Manual ZTE CORPORATION ...
Страница 4: ......
Страница 16: ......
Страница 30: ......
Страница 38: ......
Страница 46: ......
Страница 68: ......
Страница 100: ......
Страница 122: ......
Страница 174: ......