www.youfibercable.com
Email:[email protected] MSN:[email protected]
29
13) Normal “RUN”,
setting gap and
calibration, but splicing
is abnormal.
1.
Regard “TEST” as
fusion key
wrongly.
2.
Too large current.
3.
The value of
pushing is too
small or is zero
because of too
high push speed.
4.
The board is not
put well.
5.
On the right is bad
tail fiber.
1.
Confirm the fiber is
in good condition.
2.
Enter the menu to
check parameter
setting and set the
proper parameter.
3.
Do art test until
current is proper.
Reload fiber, press
“RUN” to check the
fusion.
If it doesn’t work,
contact us.
14) Normal splicing.
But the value of fusion
loss is too large and
fusion is failing.
1.
Check whether
there is fault in
system or there is
dust on the lens or
lights or reflector.
2.
The value of
“Setting end-face”
is too large.
3.
Open the
windshield before
the test.
1.Wipe the lens,
reflector and two lights;
decrease the parameter
of “Setting end-face”.
2.Do arc test until the
current is proper, and
then slice the fiber.
If it doesn’t work,
contact us.
All problems are
caused by inner
circuit fault
probably.
If you couldn’t
solve the
problems,
please sent it
to us with
detailed
explanation.
15) There is bubble on
the spliced fiber or the
fiber becomes coarse or
tenuous.
1.
The end-face of
fiber is unqualified
or there is dust on
it.
2.
The setting of
program parameter
is wrong.
Make sure that the end-
face is good.
Test current until it is
proper then try again.
If it doesn’t work,
change the value of
“Pre-fusion current,
time” or “Fusion
push”
16) The splicing index is
too large.
(actual measure)
1.
There is dust in V-
groove,
2.
Improper current
3.
The fiber is not
aligned.
4.
The electrode
doesn’t work well.
5.
Improper setting
of program
parameter.
6.
Unqualified end-
face. The cleaver
is not good.
7.
Special fiber.
8.
Bad environment.
1.Clean the V-groove,
lens or electrode.
2.Select proper program
to arc.
3.Adjust the cleaver.
4.If the splicing index is
too large, change the
value of “Pre-fusion
current” or “Fusion
push”, find proper
program.
5.Make sure that the
wind power is proper.