PVI 50/60 TL Installation and Operation Manual (Rev C)
DOCR-070645-E
Page 56 of 102
(a)
When the inverter completes “sys checking”, the LCD shows the screen as
Figure 3.1 below. Press ENTER to the standard selection interface, as shown in
Figure 3.1.
(b)
The default grid standard is IEEE 1547. If a different standard is needed please
go to “Menu Functions” section for further instructions on how to change it.
Available grid standards are shown in
Grid Connection Rule
Rule-21
HECO-ML
HECO-HM
IEEE1547
Figure 3.1 - Select Grid Standard; ML-Molokai/Lanai; OHM- O`ahu, Maui, and
Hawai`i
5.) Set up the system time and language according to “4.4.2.1 System parameters”.
6.) To check the real time operation information, you can refer to “4.4.1 Operation
information”.
7.) Communication Parameter Setting: The communication baud rate and Modbus
address can be set in this menu (Figure 3.2):
Com setting
Baud:
Addr: 32
P1/1
9600
Figure 3.2 – Selecting Baud Rate and Modbus ID