Appendix A
A.1 Checklist
A-1
175932-1CD
175932-1CD
EcoTrim ET-1024 System
Appendix A
A.1
Checklist
This checklist is provided as a convenience to help with the proper
installation, startup and maintenance of the work cell.
Time/Date
Checked By
BEFORE APPLYING POWER
(Refer to System Drawings)
Check Mounting
(Refer to Installation Section in all Mnls)
Check Power
(Refer to Connections, Controller Mnl)
Check Ground
(Refer to Grounding in all Mnls)
Check Water
(Refer to Operation and Vendor Mnls)
Check Air
(Refer to Manipulator and Vendor Mnls)
Check Gas
(Refer Operation and Vendor Mnls)
Check Interlocks
(Refer to Work Cells in all Mnls)
Check Limiting Devices
(Refer to Limits in all Mnls)
Check Environment
(Refer to Installation in Controller Mnl)
Check Version
(Refer to Confirmation of Software Version)
Other Items to Check Before Applying Power
(Vendor or Integrator Supplied)
56 of 64