For Service Engineer
Service Information
SI1604009E-002= S20, S10, M20, M10 and D10 installation procedures
4/34
2. Confirmations before shipping
When installing and adjusting machines at customers' sites, make sure to gain necessary information
and prepare thoroughly beforehand to avoid troubles.
The typical confirmations are as below.
Time of carry-in the machine
Check the schedule (date and time).
Carry-in location, carry-in route, floor and installation site
Check the required items other than a forklift and hand lifter.
Check that required quantities of curing sheets, plywood panels, and iron plates are prepared.
Line configuration of machines
Check the upstream and downstream machines of the machine to be installed and make sure
that they will not interfere with the monitor, the keyboard and etc.
Prepare the connecting tools for monitor and keyboard if needed.
Check that the signal lines between machines are standard or special order.
Check that LAN connection is prepared. Understand the usage of the database.
The power source and the air supply
Make sure that the customer is informed of the specified capacity of the power source for the
machine.
Make sure that the customer is informed of the specified diameter of the air pipe and its airflow.
Make sure that the schedule for the electric works and the air piping works are set according to
the installation schedule as required.
Weather and temperature on the day of delivering the machine
Condensation may occur on the machine depending on the morning temperature in winter
when carrying it in the installation site.
When the difference between the external temperature and the temperature in the
installation site is over 10 degrees C, condensation may occur on the machine.
If condensation may occur on the machine, prepare the place to temporarily locate the machine.
The equipment and the time to gradually warm up the machine are required on site.
Prepare a thermometer beforehand.
Note:
Regarding the confirmations above,
a lot of discrepancies among users, sales personnel and service
engineers occur.
Troubles when installing the machine occur repeatedly.
They assume that required items are prepared and fail to confirm. This is the cause of the troubles.
Make sure to confirm by yourself.