![XYZ Machine Tools ProTURN SLX 1630 Скачать руководство пользователя страница 16](http://html1.mh-extra.com/html/xyz-machine-tools/proturn-slx-1630/proturn-slx-1630_safety-installation-maintenance-service-and-parts-list-manual_3849960016.webp)
12
XYZ Machine Tools
ProTURN SLX 1630 ProtoTRAK SLX CNC Safety, Installation, Service & Parts List Manual
i00193
Figure 4
Leveling
2.9.1
SLX 1630
Use the four (4) leveling screws, located at both ends of the base, to adjust the level
of the machine.
For a newly installed machine, check the level once every week. Once the
foundation is rigid enough, then check it once per month.
2.10
Electrical Connection
The SLX 1630 can only be wired for 415 volts, 3-phase electricity.
A 110-volt power source is needed for the pendant and is provided by the
transformer.
DANGER!
Be certain that 415-volt electricity is used only with a machine labeled 415 volts and at the
electric cabinet, in the back of the machine.
The incoming 415-volt power is wired to the machine through the electric cabinet
located on the back of the machine. The wire enters the cabinet through a hole,
from the top of the cabinet. The wires are to be wired into the door breaker. The
main ground wire should be fastened to the breaker mounting bracket with the screw
provided.
DANGER!
The 415 VAC, 3-phase electricity should be wired only by a qualified electrician.