Chapter 6
Running the Tests
The skeleton design has the following setup to test the T1 card.
Figure 5: Test Setup
Dell PowerEdge R740 Server
Pktgen Application
Port 1
Pktgen Application
Port 2
QDMA Poll Mode Driver
PCIe x16
Xilinx
®
T1 Telco Card
MPSoC
PCIe x8
25G_0
25G_1
25G_2
25G_3
25G_4
25G_5
PS
RFSoC
PCIe x8
25G_0
25G_1
25G_2
25G_3
PS
DDR
2G
DDR
4G
DDR
4G
DDR
2G
SFP
X25234-033121
The following section describes each test, including setup, running, and expected results. The
primary objective of testing is to verify the following main interfaces, and then to verify data
transfer by comparing the output with expectations.
• 100G internal MAC connection between Zynq Ult MPSoC and
Zynq Ult RFSoC
Chapter 6: Running the Tests
UG1518 (v1.0) December 17, 2021
T1 Telco Accelerator Card Installation Guide
20