– Provisions of the regionally applicable building regulations
– The minimum heating water requirements in accordance with ÖNORM H5195-1 must be observed
– ÖVE regulations
– Local regulations of your power supply utility
Switzerland
The following apply to installation and operation in Switzerland:
– SVGW regulations
– VKF regulations
– BUWAL and local regulations must be observed.
4.2
Installation location
The COB-2 and TS are installed adjacent to the wall, which means that a clearance only needs to be
observed at the front.
A surface temperature of 40°C is not exceeded during proper use.
4.2.1
Minimum wall clearances to the front and side
The recommended wall clearances simplify installation, maintenance and servicing.
700
700
700
700
700
COB-2
COB-2
COB-2
TS
TS
700
COB-2
TS
Fig. 4.1
Minimum wall clearances [mm]
4.2.2
Minimum clearances (above)
1
COB-2-40: 1900
COB-2-15/20/29: 1800
COB-2-15/20/29: 300
COB-2-40: 400
Fig. 4.2