52
A
Fig. 37
A
Combustion air aperture
For balanced flue systems tested together with the
heat generator, there is no requirement for a tightness
test (overpressure test) during commissioning by the
flue gas inspector.
In this case, we recommend that a simple tightness
test is carried out during system commissioning. For
this, check the CO
2
or O
2
concentration in the combus-
tion air at the annular gap of the balanced flue pipe.
If the CO
2
concentration is less than 0.2 % or the O
2
concentration is greater than 20.6 %, the flue pipe is
deemed to be sufficiently gas-tight.
If actual CO
2
values are greater or O
2
values are lower,
then pressure test the flue pipe with a static pressure
of 200 Pa.
!
Please note
If the test port is not sealed, combustion air is
drawn in from the room.
After the tightness test, re-seal the test port with
the plug.
Removing the burner
Note
If the programming unit is located at the top: Move the
programming unit down into the maintenance position.
See page 46.
Commissioning, inspection, maintenance
Leak test on balanced flue system (annular gap check)
5593201
Содержание B2HF
Страница 33: ...33 2 2x 1 Fig 26 Installation sequence Closing the wiring chamber 5593201 Installation ...
Страница 45: ...45 1 2x 1 2 3 2x 2 3 Fig 32 Commissioning inspection maintenance Removing the front panel 5593201 ...
Страница 111: ...111 1 2 4 3 6 5 Fig 56 Troubleshooting Repairs cont 5593201 Diagnosis ...
Страница 134: ...134 WiFi router 31 Wiring diagram 121 Keyword index Keyword index cont 5593201 ...
Страница 135: ...135 5593201 ...