Vertiv
|
XTE 802 Series Walk-In-Cabinet (WIC) Description & Installation Manual (631-205-434)
|
Rev. D
77
Lifting the WIC
Safety Precautions
DANGER!
The maximum WIC weight when lifted shall not exceed equipment ratings!
Procedure (When Using a Crane)
1.
Close and latch all doors before lifting and placing the WIC.
2.
Inspect the lifting eyebolts and ensure eyebolts and roof are secure and free of damage.
3.
Install a clevis and shackle or a threaded shackle in each eyebolt at the top of the WIC as shown in
4.
Insert all four (4) 8 feet minimum lifting slings securely through all four clevises or shackles as shown in
.. Never route straps, cables or chains through the forklift channels in the base for a vertical
crane lift.
NOTE!
If slings are not long enough (8-ft. [2.4 m] or longer), use a spreader bar to be sure the cables
pull on the lifting eyebolts in a vertical direction.
NOTE!
It is important that the length of each sling allow for an angle 45 degree or more.
NOTE!
Failure to maintain a 45 degree angle or greater and using all four eyebolts will void any
warranty or service claim.
5.
Tie a 75-ft. rope to a lifting eyebolt so it can be used as a tag line.
6.
Never work under the WIC while it is suspended above the ground.
7.
Lift the WIC off the truck and place it into its mounted position using the tagline to guide it into position.
Continue with the “Placing the WIC” procedure on 79.
Procedure (When Using a Forklift)
1.
Close and latch all doors before lifting and placing the WIC.
2.
Lift the WIC using the forklift pockets located in the base of the WIC.
3.
Never work under the WIC while it is suspended above the ground.
4.
Lift the WIC off the truck and place it into its mounted position. Continue with the “Placing the WIC”
procedure on 79.