adequate parking to ensure safety for people and vehicles. Place the WIC and Generator where it will
not create a visual or physical obstruction to either vehicles or pedestrians.
•
Select locations that will minimize accidental or intentional vandalism. Consider the use of protective
posts/bollards when the WIC and Generator is located near parking areas where vehicles could back into
it.
•
Do not place the WIC and Generator in ditches or areas subject to flooding. If installation is in a flood
zone, use the Elevated WIC and Generator Platform.
•
on page 25 shows the minimum working space allowed between the WIC and Generator and
any obstruction including fences, hedges, etc. Working space consists of adequate area for craft
personnel to perform work and maintenance procedures as defined in the National Electric Code (NEC).
•
Where ordinances or other standards require that the WIC and Generator be placed behind vegetation,
preference should be given to evergreens that will not produce leaves, sticky pollen or waste that could
fall and clog the climate control units vents.
•
If the area is subject to freezing temperatures, be sure to comply with the local building codes and
footing requirements to eliminate the possibility of frost heave.
•
Minimize snow buildup around the WIC and Generator and its externally mounted components.
•
Placement should support access for snow removal equipment in the event of a snow/ice storm.
WIC Foundation Kit Installation
WIC Helical Foundation Kit Installation (P/N D1000-0000-0101)
WIC Helical Foundation Kit Installation Procedure
1.
Assemble the universal driving tool on the correct Kelly bar adapter.
2.
Connect Kelly bar adapter to Kelly bar on the drive head.
3.
Move drive tool assembly to first helical and attach universal driving tool to helical plate paying attention
to keeping the Kelly bar as centered in the helical as possible. The leveling hardware can be used for
this temporary attachment.
4.
Lift helical upright allowing it to swing free of the ground.
5.
Maneuver the helical directly over the installation point.
6.
Lower the helical until the point of the helical is forced into the ground on target.
7.
Screw helical 12 inches into the ground and plumb using a level on 2 sides 90 degrees from each other.
8.
Continue screwing the helical into the ground while correcting the Kelly bars orientation so the helical
embeds itself straight. A ground man can be of assistance in keeping the foundation plumb during the
installation.
9.
Drive the helical until the helical plate is 11 inches above grade orientated as shown in
. Stop