ULB PROPRIETARY RIGHTS NOTICE
- This document contains the confidential and proprietary information of ULB. You may not
possess, use, copy or disclose this document or any information in it for any purpose without express written permission. Neither receipt
from any source, nor possession of this document, constitutes such permission. Possession, use, copying or disclosure by anyone
without express written permission of ULB is not authorized and may result in criminal and/or civil liability.
C:\Users\Service-Eng\Desktop\Mx\Manuals\ULB-R110 MANUAL_rev02.docx Page
13
of
42
Operation
Connect the power source under test to CAM-LOK connectors provided on the load bank
using suitable mating CAM-LOK plugs and cables sized per the NEC (National Electric
Code) or any local codes.
The Load Bank is provided with color coded qty.01 CAM-LOK connectors (400A Max.) for
each phase (L1/L2/L3) and One Connector for Ground Cable connection.
Load cable conductors from the power source to the load bank and mating CAM-LOK
cable plugs should be adequately sized and protected to handle the maximum rated load
and in accordance to the
National Electric Code and any local codes
.
Turn on the power source under test.
Connect external 120VAC,1-Phase, 50/60Hz, 10A Power Source using supplied
cord with plug to the load bank.
HMI Display (E1A) on hand held unit will turn on.
Use main screen on HMI display (as shown below figure-1) to set require KW.
Figure-1 Main Screen.