V. INSTALLATION OF “TMR090 SERIES”
1. Preparatory Procedure
(1) Make sure the transportation plan for “TMR090 Series” including a carry-in route.
(2) Arrange all necessary equipments for unloading “TMR090 Series” from the truck,
such as a forklift.
(3) Prior to installation, please confirm that all necessary works in the membrane
submerged tank are completed. All waste from the tank, such as concrete clusters,
scrapes and mill ends, should be removed completely. Also, please confirm that
there is no leakage of water or air from the tanks or pipes.
2. Unloading/lifting Products
Unload "TMR090 Series” with suitable equipment such as forklift.
Please note the followings for unloading "TMR090 Series".
(1) The element block and the aeration block are separately packed together in
cardboard box and delivered. The element block contains a fixed number of
membrane elements installed in it.
(2) Do not hoist the delivered cardboard box which contains element block(s) and
aeration block(s). Please use forklift for moving the box on site.
(3) Do not stand or sit on the top of the box.
(4) When lifting "TMR090 Series", please set a hook on all hang holes and lift it
keeping it horizontal with chains or slings. Please use special hanger (drawing
attached) in case of limited hanging space.
(5) Please be careful not to damage element nozzles, air diffusers, permeate
manifolds or other components.
(6) Please ensure safety anytime when doing these operations.
When lifting “TMR090 Series”, please attach chains or slings to it
and lift it straight upward
calmly
to prevent “TMR090 Series” from
shaking. Never allow any person under “TMR090 Series”.
Please use chains or slings compatible with lifting weight.
Be sure to set down the module where there is no obstacle.
Otherwise, the module may topple down and get damaged.
DANGER
!
DANGER
!
DANGER
!