USE AND INSTALLATION MANUAL ELFO
33
4.23 CHECKS AT THE END INSTALLATION
4.24 STARTING THE CONDENSING
A few simple checks ensure correct system operation:
- Check the electrical connections.
- In multi-split models perform testing before evaporating
with one on and then the next (this will highlight any incorrect
connections to the ventilation units)
- Ensure the proper flow of water into the drain used.
- Check the operating pressure (high pressure) by means of
the manifold to verify the correct operation of the pressure
valve
1.
Connect the power supply, press the “ON / OFF” button on
the remote control to start the operation.
2.
Press the “MODE” button to select AUTO, COOL, DRY,
FAN and HEAT to see if the operation creates a malfunction
of the machine.
- Make sure the unit is installed securely.
- The thermal insulation of the pipeline is enough? It can
cause condensation and water leaks.
- Check the grounding.
- Check for any obstruction to the air intake.
- The gas valves and connecting fluid are completely open?
3.
If the ambient temperature is below 16 ° C, the air
conditioner can not cool the water.
4.22 LEAK DETECTION
1.
Check for leaks with leak detector.
2.
If the leakage probe is not available, please use soap and
water for leak detection.
Apply soap and water in the suspected position and maintain
the soap and water for more than 3 minutes. If there are
bubbles coming out from this position, identify and restore
the loss.