background image

 

1.1.2 Unpacking the Cabinet 

To unpack the system: 
1.  Open the outer carton and remove the accessories packaged with the 

cabinet. 

2.  Carefully lift the cabinet out of the outer carton and set it on a flat, stable 

surface. 

3.  Discard or recycle the packaging in a responsible manner, or store it for 

future use. 

1.1.3 UPS Setup 

All  model  series  are  designed  for  tower  and  rack  purpose.  They  can  be 
installed  into  a  19  inches  equipment  rack.  Please  follow  the  instruction  for 
Tower Setup and Rack-Mount Setup.   

l

 

Tower setup 

This  series  of  UPS  can  be  placed  horizontally  and  vertically.  As  a  tower 
configuration,  it  is  provided  with  the  optional  UPS  stands  to  stabilize  the  UPS 
when the UPS is positioned in vertical. The UPS stand must be attached to the 
bottom of the tower. Use the following procedure to install UPS in UPS stands. 

1. 

Slide  down  the  UPS  vertically  and  put  two  UPS  stands  at  the  end  of  the 
tower.

             

 

2. 

Place down the UPS into two stands carefully.     

3. 

Pull out the LCD box and rotate it in a clockwise direction to 90 degree and 

then push it back in the front panel

.

   

 

 

 

 

 
 
 
 
 
 

 

l

 

Rack-mount setup 

The series  can be  installed  in  19  inches racks.  Both the  UPS and  external 
battery enclosure need 2U of valuable rack space.     

Use the following procedure to install UPS in a rack. 

1.  Align  the  mounting  ears  with  screw  holes  on  the  side  of  the  UPS,  and 

tighten the screw. 

2.  Assemble the rack rails with the rack-mounting. 
3.  Slide in the UPS into the rack rail and lock it in the rack enclosure. 
4.  Tighten the screw, and the load can then be connect 
 

                                                               
       
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

1.1.4 EBM Installation (Optional) 

l

 

Connecting the EBM in Tower form: 

1.  Slide down the UPS and EBM vertically and place two UPS stands with the 

extend part at the end of the tower. 

2.  Tighten the screw on the metal sheet for stabilization 

3.  Connect the Earth line from UPS (port A ) to EBM (port B) 

4.  Take off the front panel, and connect the battery terminal (A) from UPS to 

EBM terminal (B) shown as below. Users need to remove the small gate(C) 

Содержание AP160N Series 1000VA

Страница 1: ...iption 17 5 Connection and Operation 19 5 1 Inspection 19 5 2 Connection 19 5 3 Battery charge 21 5 4 Turn on the UPS 21 5 5 Test function 21 5 6 Turn off the UPS 22 5 7 Audible alarm mute function 22...

Страница 2: ...ssure to connect with the earth reliably Assure external battery source must be earthed Connect the UPS only to an earthed shockproof socket outlet The building wiring socket outlet shockproof socket...

Страница 3: ...the end of the tower 2 Place down the UPS into two stands carefully 3 Pull out the LCD box and rotate it in a clockwise direction to 90 degree and then push it back in the front panel 5 l Rack mount...

Страница 4: ...battery terminal A from UPS to EBM terminal B shown as below Users need to remove the small gate C on side of the front panel to allow the outlet wire of the EBM to pass through the gate and then reas...

Страница 5: ...the gate and then reassemble front panel B C A D E 9 Note Three or more EBMs can be connected to the UPS in the same way as shown above Note After connect the EBMs please do not forget to set the num...

Страница 6: ...alified maintenance personnel 1 3 1 UPS and Battery Care For the best preventive maintenance keep the area around the UPS clean and dust free If the atmosphere is very dusty clean the outside of the s...

Страница 7: ...ake on off the load To test batteries 1 Connect the UPS to utility power for at least 48 hours to charge the batteries 2 Press and hold the I button 1 second to start the battery test on line mode or...

Страница 8: ...D IEC EN 61000 4 2 Level 3 RS IEC EN 61000 4 3 Level 3 EFT IEC EN 61000 4 4 Level 4 SURGE IEC EN 61000 4 5 Level 4 CS IEC EN 61000 4 6 Level 3 MS IEC EN 61000 4 8 Level 3 Voltage Dips IEC EN 61000 4 1...

Страница 9: ...KS Extended backup time 17 4 Panel Description The Display Panel Switch Function ON Button Turn on UPS system By pressing the ON Button I the UPS system is turned on Deactivate acoustic alarm By press...

Страница 10: ...orm the transport agency immediately should you find signs of damage Please keep the packaging in a safe place for future use Note Please ensure that the incoming feeder is isolated and secured to pre...

Страница 11: ...ed 5 4 Turn on the UPS 1 With utility power connecting Press I button continuously for more than 1 second to turn on the UPS the UPS will get into the inverter mode the LCD screen will indicate the st...

Страница 12: ...will cause abnormality or permanent damage 2 One hard wiring type battery terminal on the rear panel is used for connecting the battery pack 3 The battery connection procedure is very important Any i...

Страница 13: ...nominal power capacity 25 Note Please follow the following steps to connect the generator l Activate the generator and wait until the operation is stable before supplying power of the generator to th...

Страница 14: ...hile the utility power is in normal range so the high efficiency could be gained in the ECO mode Once the mains is loss or abnormal the UPS would transfer to battery mode and the load is supplied cont...

Страница 15: ...for more than 10 seconds the setting mode exit automatically The output frequency string OPF Bypass status string bYPA operating mode string MOdE Battery string bSTR Load segment string LS1 and LS2 wo...

Страница 16: ...battery voltage is normal and the mains is normal charge automatically again Battery low Battery voltage is low When audible alarm sounding every second battery is almost empty 31 Charge fail The cha...

Страница 17: ...d start the UPS If it needs to replace the batteries while the UPS is running make sure the UPS would not shut down during the replacement If there is a battery breaker then turn it off first Disconne...

Страница 18: ...a computer connect one end of the serial communication cable that comes with the UPS to the RS 232 port on the UPS Connect the other end of the serial cable to the RS 232 port on a computer The cable...

Страница 19: ...er WinPower is a brand new UPS monitoring software which provides user friendly interface to monitor and control your UPS This unique software provides safely auto shutdown for multi computer systems...

Страница 20: ...1 AC Output 2 EPO Dry input Communication Port 3 USB Port 4 AC Input 5 Dry out 6 SNMP slot 7 RS232 8 Modem Network Surge Protection 9 Earth Line connection 39 1 1 3K Standard model rear panel 3K KS mo...