4.
Go the the other side of the carrier. Place the two
individual control levers of the outriggers on your side to
EXTENSION. Then move the extend/retract control
lever toward EXT. to extend the outrigger beams fully.
◆
The figure below shows an outrigger on the right side
of the carrier.
5.
Insert the lock pins to lock the extended outrigger
beams.
6.
Place all four individual control levers in the JACK
position. Move the extend/retract control lever toward
EXT. to fully extend the jack cylinders.
7.
After all four jack cylinders are fully extended, return
the extend/retract control lever and all the individual con-
trol levers to the neutral position.
8.
Use the bubble levels to make sure that the crane is
level. If the crane is not level, refer to the "Level
Adjustment" section for detailed instructions on leveling
the crane.
Middle Extension Procedure
1.
Extend the outrigger beams to the mid. extended
mark (4.6 m) in the same procedure as the full extension
procedure.
2.
Insert four lock pins into the pin holes to lock the
outrigger beams.
3.
Extend all the jack cylinders fully in the same proce-
dure as the full extension procedure.
T038330E
61
Outriggers
Outriggers
Marking line
Bubble
T05569E
EXTENSION
JACK
FRONT JACK
EXT.
RET.
T30111E
T30112E
Mid. extended mark (4.6m)
EXTENSION
JACK
FRONT JACK
EXT.
RET.
T30110E
Содержание GT-550E-2
Страница 20: ...A 19 Safety Rules Safety Rules...
Страница 23: ...A 22 Safety Rules Safety Rules...
Страница 29: ...A 28 Safety Rules Safety Rules...
Страница 30: ...A 29 Warning Labels Warning Labels...
Страница 32: ...A 31 Warning Labels Warning Labels 1 2 3 JIB PIN STATUS...
Страница 36: ...1 Contents Contents...
Страница 37: ...2 Contents Contents...
Страница 38: ......
Страница 41: ...6 Layout of Controls Layout of Controls of Controls Layo out...
Страница 46: ...H000450E OPERATION...
Страница 73: ......