Commissioning
Page 27/55
SYCLOPE TERE’O Touch XL
®
Installation, starting, and programming instructions
VI.
Commissioning
You have just carried out electrical connections, you have installed sensors and you have connected
dosing equipment, you are thus ready to carry out the startup of your
SYCLOPE TERE’O Touch
®
controller.
Apply the power supply on the controller
Check if no visual problem appears, if the controller is well lit and if the other equipment’s of
the installation are not disturbed.
SYCLOPE TERE'O Touch
®
controller does not launch automatically the chemistry
treatments. The user is the main master for launching the controller after checking the good
programming according the needs.
SYCLOPE TERE’O Touch
®
is full programmable. During the power up, the present parameters are
fixed and all regulation processes are inactive.
SYCLOPE TERE’O Touch
®
controller is delivered with standard programming.
It is advisable
for the user to modify this programming if it does not correspond to the needs.
To modify
the programming of the controller, please refer to the following chapter.
VII.
Programming the controller
TERE’O Touch
®
controllers are equipped with a touch-sensitive colour graphic display, so all
programming actions are performed by pressing the display. The technology of the touch screen is
resistive type, it is necessary to make a firm pressure on the screen to validate the keys.
Ensure the good programming of the
TERE’O Touch
®
controller before starting regulations!
An excess of chemical products can cause harmful actions on the human health and the
environment.
1)
Principal display
The display is made by a backlit 4.3-inch colour graphic display separate into three main parts:
The upper panel
The left panel for
pH measurement
The right panel for
chlorine or bromine
measurement.