31
February 2020
|
Solar Stik
®
, Inc.
System Setup and Operation Manual for ATSC MS3 L0
c Connect PRO-Verter to shelter service panel
Connect the PRO-Verter (“220 AC OUT” port) to the shelter service panel using a green-to-green
connection.
PRO-Verter
left side view
Shelter/Conex
service panel
AC Output Power Cable
Figure 15. PRO-Verter to shelter service panel connection
For detailed setup instructions, see the 420W Expedition Solar Array-C Operator Manual. The panels
should be positioned for maximum daily sun exposure.
DO NOT secure the Solar Arrays to the
ground until the entire System is setup
d Connect / Assemble Solar Arrays
Connect the four (4) PV panels on a single rack “in series” using the wiring diagram below. There will
be one (1) “free” connector at each end of the rack of panels (
*
in figure below). Connect these two
(2) free ends to the appropriate connectors of the 30’ Solar Leash.
Figure 16. Connect negative and positive ends of the cables as shown
30’ Solar Leash
*
*
To the Power Hub