SI4248U Manual
Installation Manual
63
Figure 1-27 State transition for generator start and load shedding
When critical state is reached (and no charge current is detected) the Sunny Island 4248U will
shut down for battery protection. After that a manual restart of the Sunny Island 4248U is
required. If no charge current flows the inverter will shutdown after 5 minutes. Independent
from the Generator and Load Shedding control the battery voltage monitoring stays active and
will shut down Sunny Island 4248U, if the battery voltage falls below the minimum voltage level
VbatMin.
SOC < SocLim1
for t > 2/6/30 minutes
Normal
Warning
(Start Generator)
Low
(Load Shedding)
Critical
(Shut down)
SOC < SocLim2
for t > 2/6/30 minutes
SOC < SocLim3
for t > 2/6/30 minutes
and no charging current
SOC > SocLim1
for t > 15 minutes
SOC > SocLim2
for t > 15 minutes
SOC > SocLim3
for t > 15 minutes
or charge current
Содержание Sunny Island 4248U
Страница 2: ...SI4248U Installation Guide ii...
Страница 6: ...SI4248U Installation Guide vi...
Страница 74: ...Battery Management SI4248U Manual 66...
Страница 98: ...Battery Management SI4248U Manual 90...
Страница 99: ......
Страница 100: ......